PREAMBLE (NOT PART OF THE STANDARD)

This library of books, audio, video, and other materials from and about India is curated and maintained by Public Resource. The purpose of this library is to assist the students and the lifelong learners of India in their pursuit of an education so that they may better their status and their opportunities and to secure for themselves and for others justice, social, economic and political.

This item has been posted for non-commercial purposes and facilitates fair dealing usage of academic and research materials for private use including research, for criticism and review of the work or of other works and reproduction by teachers and students in the course of instruction. Many of these materials are either unavailable or inaccessible in libraries in India, especially in some of the poorer states and this collection seeks to fill a major gap that exists in access to knowledge.

For other collections we curate and more information, please visit the Bharat Ek Khoj page. Jai Gyan!

END OF PREAMBLE (NOT PART OF THE STANDARD)

IRC: 89-1997

GUIDELINES FOR DESIGN AND CONSTRUCTION OF RIVER TRAINING AND CONTROL WORKS FOR ROAD BRIDGES

(First Revision)

Published by:

INDIAN ROADS CONGRESS
Jamnagar House, Shahjahan Road,
New Delhi-110011
1977

Price Rs.120/-
(plus packing & postage)

BRIDGES SPECIFICATIONS AND STANDARDS COMMITTEE
(as on 18-4-95)

Sl. No. Name Address
1 M.V. Sastry*
(Convenor)
DG (RD), Ministry of Surface Transport (Roads Wing), New Delhi-110 001
2. M.R. Kachhwaha
(Member-Secretary)
Chief Engineer (B) S&R, Ministry of Surface Transport (Roads Wing), New Delhi
3. S.S. Chakraborty Managing Director
Consulting Engg. Service (I) Pvt. Ltd., 57, Nehru Place, New Delhi-110 019
4. A.D. Narain Chief Engineer (Bridges), MOST (Roads Wing), New Delhi-110001
5. Prof. D.N. Trikha Director, Structural Engg. Res. Centre, Sector-19, Central Govt. Enclave, Kamla Nehru Nagar, PB No. 10, Ghaziabad-201 002
6. R.H. Sarma Chief Engineer, MOST (Retd.),
C-7/175, Safdarjung Dev. Area, New Delhi-110 016
7. Ninan Koshi DG(RD) & Addl. Secy, MOST (Retd),
56, Nalanda Apartment, Vikaspuri, New Delhi
8. S.N. Mane Sr. Vice President
Lok Global & National Constn. Ltd., Lok Centre, Marol-Maroshi Road, Andheri (E), Mumbai-400 059
9. G. Bhatwa Chief Engineer (NH)
P.W.D., B&R Branch, Patiala
10. A.G. Borkar A-l, Susnehi Plot No. 22, Arun Kumar Vaidya Nagar, Bandra Reclamation, Mumbai-400 050
11. N.K. Sinha Chief Engineer (PIC)
Ministry of Surface Transport (Roads Wing), Transport Bhavan, New Delhi-110 001
12. P.B. Vijay Addl. Director General (Border),
Central Public Works Deptt., Nirman Bhavan, Room No. 424, New Delhi-110011.
13. H.P. Jamdar Secretary to the Govt. of Gujarat,
R&B Deptt., Block No. 14, Sachivalaya Complex, Gandhinagar-382 010
14. G.C. Mitra Engineer-in-Chief (Retd.)
A-l/59, Saheed Nagar, Bhubaneswar-751 007
15. Surjeet Singh Secretary to the Govt. of Madhya Pradesh,
E-2/CPC, Char Imli, Bhopal-462 016
16. V. Murahari Reddy Engineer-in-Chief (R&B),
Errum Manzil, Hyderabad-580 482
17. M.V.B. Rao Head, Bridge Division,
Central Road Research Institute, P.O. CRRI, Delhi-Mathura Road, New Delhi-110 020
18. Prof. C.S. Surana Civil Engg. Department,
Indian Institute of Technology, Hauz Khas, New Delhi-110 016
19. C.R. Alimchandani Chairman & Managing Director, STUP Consultants Ltd., 1004-5 & 7, Raheja Chambers, 213, Nariman Point, Mumbai-400 021
20. N.C. Saxena Director
Intercontinental Consultants & Technocrats (P) Ltd., A-ll, Green Park, New Delhi-110 016
21. M.K. Bhagwagar Consulting Engineer,
Engg. Consultants (P) Ltd., F-14/15, Connaught Place, New Delhi-110 001
22. B.S. Dhiman Managing Director,
Span Consultants (P) Ltd., Flats 3-5, (2nd Floor), Local Shopping Centre, J-Block, Saket, New Delhi-110 017
23. S.R. Tambe Secretary (R),
P.W.D., Mantralaya, Mumbai-400 032
24. S.A. Reddi Dy. Managing Director,
Gammon India Ltd., Gammon House, Veer Savarkar Marg, Prabhadevi, Mumbai-400 025
25. Dr G.P. Saha Chief Engineer,
Hindustan Construction Co. Ltd, Hincon House, Lal Bahadur Shastri Marg, Vikhroli (West), Mumbai-400 083
26. P.Y. Manjure Principal Executive Director,
The Freyssinet Prestressad Concrete Co. Ltd., 6/B, 6th Floor, Sterling Centre, Dr. Annie Besant Road., Worli, Mumbai
27. Papa Reddy Managing Director
Mysore Structurals Ltd., 12, Palace Road, Bangalore-560 052
28. Vijay Kumar General Manager UP State Bridge Constn. Co. Ltd., 486, Hawa Singh Block, Khel Gaon, New Delhi-110049
29. P.C. Bhasin 324, Mandakini Enclave, Greater Kailash-II, New Delhi-110 019
30. D.T. Grover D-1031, New Friends Colony, New Delhi-110 065
31. Dr V.K. Raina B-13, Sector-14, NOIDA (UP)
32. N.V. Merani A-47/1344, Adarsh Nagar, Worli, Mumbai -400 025
33. C.V. Kand Consultant
E-2/136, Mahavir Nagar, Bhopal-462 016
34. M.K. Mukherjee 40/182, Chitranjan Park, New Delhi-110 019
35. Mahesh Tandon Managing Director
Tandon Consultant (P) Ltd., 17, Link Road, Jangpura Extn., New Delhi-110 014
36. U. Borthakur Secretary, PWD B&R (Retd.)
C/o Secretary, PWD B&R, Shillong-793 001
37. Dr. T.N. Subba Rao Construma Consultancy (P) Ltd., 2nd Floor, Pinky Plaza, 5th Road, Khar (W), Mumbai-52
38. S.C. Sharma Chief Engineer (R) S&R,
Ministry of Surface Transport (Roads Wing), New Delhi-110 001
39. The Director Highways Research Station, Guindy, Madras-25
40. G.P. Garg Executive Director (B&S),
Research Designs & Standards Organisation, Lucknow-226 011
41. Vinod Kumar Director & Head (Civil Engg.),
Bureau of Indian Standards, Manak Bhavan, New Delhi-110 002
42. President,
Indian Roads Congress
K.K. Madan -Ex-Officio
Director General (Works), CPWD,
New Delhi-110 011
43. DG(RD) & Hon. Treasurer,
Indian Roads Congress
M.V. Sastry - Ex-Officio
44. Secretary,
Indian Roads Congress
S.C. Sharma - Ex-Officio
Corresponding Members
1. Shitala Sharan Adviser Consultant,
Consulting Engg. Services(Ι) Pvt. Ltd., 57, Nehru Place, New Delhi-110019
2. Dr. M.G. Tamhankar Dy. Director & Head,
Bridge Engg. Division, Structural Engg. Research Centre, Ghaziabad (U.P.)
* ADG(B) being not in position. The meeting was presided by Shri M.V. Sastry, DG(RD) Govt of India MOST

1. INTRODUCTION

“The Guidelines for Design and Construction of River Training and Control Works for Road Bridges” were first published in 1985. These guidelines did not include floor protection works and maintenance of the protective works. Also need for verifying the recommendations of physical model studies on mathematical model has been felt. Further, new materials like geo-synthetics now find use in the strengthening of earthen embankment, slope protection and launching apron. As such need for revising the existing guidelines was felt. Accordingly, a Committee comprising of the under mentioned members was formed to review the existing guidelines:

L.S. Bassi ... Convenor
M.P. Marwah ... Member-Secretary
MEMBERS
S.P. Chakrabarti Rep. of Central Water Power Res. Station
K.P. Poddar (S.B. Kulkarni)
N.K. Sinha Rep. of RDSO (V.K. Govil)
H.S. Kalsi B.K. Bassi
G. Bhatwa Rep. of Central Water Commission
H.N. Chakraborty (G. Seturaman)
S. Manchaiah Research Officer, Hydraulic Div. Irrigation
M. ChandersekheranCE (Design) Bldg. and and Power Institute Rep. of DGBR (S.P. Mukherjee)
   Administration, Rep. of IRI (Harish Chandra)
   Andhra Pradesh, PWD
Director, H.R.S., Madras
EX-OFFICIO MEMBERS
President, IRC (M.K. Agarwal) Hon. Treasurer, IRC (Ninan Koshi)
Secretary, IRC (D.P. Gupta)
CORRESPONDING MEMBERS
J.S. Marya B.J. Dave
J.S. Sodhi Coastal Engineer, B.P.T.

The Protective Works Committee (B-9) reviewed the existing guidelines and finalised the modifications in their meeting held on 13-8-93. These guidelines have since been approved by the Bridges Specifications & Standards Committee in their meeting held on 18.4.95. These were approved by the Executive Committee and the Council of the Indian Roads Congress in their meetings held on 19-4-95 and 1-5-95 respectively.

2. SCOPE

2.1.

The guidelines cover the layout and design of river training works and approach embankment protection works for ensuring safety of the bridges and their approaches. These guidelines also deal with some of the construction and maintenance aspects. Protection works for open and shallow foundations are also covered.

2.2.

The scope of these guidelines is limited only to some salient aspects of design and construction of the protection works mentioned above and does not extend to the much wider associated problems of river behaviour, control and bridge hydraulics, etc.

2.3.

The necessity or otherwise of the guidebunds, spurs and other protective works has to be decided upon carefully after observing the behaviour of the river at the site under consideration. Data about the protection works at other sites on upstream or downstream of the site under consideration can also be a good guide.

River training works are costly and their maintenance cost is also very high. In case, their location, configuration and size is not decided properly, these works can cause damaging effects also. Therefore, they have to be provided judiciously.

For bridges across major rivers, the extent and configuration of the protective works should be decided with the help of physical models. For accuracy, the results obtained from physical models may be further checked on mathematical models by the same research station which carried out physical model studies.

2.4.

Given inadequate knowledge of and uncertainties around many2

aspects of bridge hydraulics and river behaviour characteristics in general, these guidelines cannot obviously claim to have any general validity of application. These are to be deemed as a guide to good practice of design and construction of the protection works compatible with the current experience and knowledge in the subject area. For particular applications, these guidelines may have to be modified and supplemented in each case based on subjective and objective judgement of the engineer, to cater for site, river and specific requirements of a bridge structure.

3. TERMINOLOGY

3.1.

The following definitions shall apply for the purpose of these guidelines.

  1. Afflux/backwater: The rise in flood level of the river immediately on the upstream of the bridge as a result of obstruction to natural flow caused by the construction of the bridge and its approaches.
  2. Alluvial streams: A stream whose bed and banks are composed of loose granular material, that has been deposited by the stream and can be picked up and transported again by the current during the floods, and is said to flow through incoherent alluvium, may be briefly referred to as an alluvial stream.
  3. Approach road protection: Approaches are protected by means of pitching and turfing against ravages due to wind, rain-cuts, wave action, erosive action of parallel flow or frontal attack of a river. Further, where a bridge with constricted water-way is located in a wide khadir, guide bunds alone may not afford protection to the entire length of approaches from the river flow. In such cases, approaches beyond the influence zone of guide bunds may need protection.
  4. Floor protection works: Protection in the form of flooring where adoption of shallow foundations, becomes economical by restricting the scour.
  5. Guide bunds: These are embankments meant to confine and3

    guide the river flow past a bridge without causing damage to it and its approaches. These are generally constructed in the direction of flow on one or both flanks, depending on the site conditions.

  6. Khadir: The maximum width over which the river meanders during high floods is known as Khadir width of the river.
  7. Meander: The curvature of flow, established in a stream either due to its own characteristics or due to impressed external forces.
  8. River bank protection: Bank protection is afforded directly in the form of slope pitching/turfing or indirectly in the form of spurs.
  9. Spurs or Groynes: These are structures constructed transverse to the flow of the river and extend from the bank into the river. These are intended to induce silting and diverting the flow away from the point of attack.

4. SITE DATA

The following information in line with the provisions of IRC:5-1985, and amplified hereinafter shall be furnished. The nature and extent of the data to be collected in each case will, however, depend upon the importance of the bridge.

4.1. Topographical Data

  1. An Index map, to a suitable small scale (topo sheets scale 1 cm to 500 m or 1/50,000 would do in most cases) showing the proposed project location, reach under consideration, the existing means of communication, the general topography of the country and important towns, any other existing or proposed structure across or along the river, etc., in the vicinity of the proposed works.
  2. River survey plans, preferably to a scale 1/10,000 for a river reach of at least two meander lengths upstream and one meander length downstream. In case the bridge is situated immediately downstream of the4

    confluence of two rivers, the reach to be considered in respect of both of these should be at least 1.5 km upstream of the extent of back water influence in the tributaries under highest flood level.

  3. A contoured site plan, to a suitable scale showing the location of the bridge and covering approaches to a sufficient distance (not less than 500 m on either side beyond the Khadir width in the case of a bridge across major river), the direction of flow, names of nearest inhabited localities, references to the bench marks used as datum, location of trial pits for borings and the location of nullahs, wells and outcrop of rocks and the existence of structures upstream and downstream of the river.

    The site plan should extend for a distance of atleast 3 km upstream and 1 km downstream and should indicate river course during high floods and dry season duly superimposed in different colours for as many years as available. The contours or spot levels should extend over this area at a contour interval varying from 0.5 m in flat terrain to 2 m for steep terrain.

    The nodal points which are not affected by meandering action of the river should be suitably marked on the plan.

  4. Cross sections, showing bed and bank levels, L.W.L. and H.F.L. at the bridge site and at L/10 interval for a distance of 1.5 L on upstream and for a distance of L on downstream subject to a maximum spacing of 30 m intervals where L is the length of the bridge.

4.2. Hydrological Data

  1. The size, shape and surface characteristics of the catchment area including percolation and interception, area drainage pattern and the likely effect of proposed protective works on the same.
  2. The possibility of subsequent changes in the catchment like the regrouping or canalisation of the streams, afforestation, deforestation, urban development, extension of or reduction in cultivated areas.
  3. Storage in the catchment area, artificial or natural.5
  4. The slope of the catchment both longitudinal and cross.
  5. The intensity duration and frequency of rainfall in the catchment.
  6. Hydrographs for one or more years if possible and in the absence of such data, fluctuations of the water level observed during different months of the year.
  7. The highest flood level (on record for a period not less than 50 years) and the year of its occurrence. If the flood is affected by the back water, details of the same.
  8. A chart showing High Flood Levels, corresponding discharges and their duration for as many as years as available together with maximum and mean velocities corresponding to the aforesaid flood discharges.
  9. The influence of afflux on areas in the vicinity likely to be affected.
  10. Low water level.
  11. River bed slope, flood slope and natural ground slope of flood plain, if any.
  12. Direction of the main current during low, medium and high floods.
  13. In case the reach of river to be trained is tidal, information regarding H.T.L. & L.T.L. of spring as well as high tides both during freshets and dry season.
  14. Nature and extent of bank erosion noticed in a distance of 2 meanders (or 1 km whichever is more) upstream and 1 meander downstream for meandering rivers and 5 L (or 1 km whichever is more) upstream and 3 L downstream for non-meandering rivers.
  15. The observed maximum depth of scour with corresponding H.F.L. and details of obstruction or any other special causes responsible for this scour.6
  16. Studies of channel trends based on experience with comparable situations and also on the basis of maps and published reports, if any.
  17. Description regarding terrain, slope, stability of river banks, natural or artificial.
  18. Details of change in the river course, if any, found in the vicinity of the proposed structure.

4.3. Geotechnical Data

  1. Soil strata chart/trial pit/bore hole particulars available, if any, in the vicinity of the proposed structures.
  2. Bore hole data along the length of proposed protective works upto maximum anticipated scour level alongwith shear strength parameters (cohesion and angle of internal friction), consolidation characteristics of sub-soil strata, the particle size distribution and mean diameter.
  3. Sediment load characteristics, river behaviour in the vicinity of the bridge i.e. whether aggrading, degrading, senile or braided, etc. Specific limitations, if any, imposed by the type of the river may also be indicated.

4.4. Environmental/Ecological Data

Existing environmental/ecological conditions in the immediate vicinity of the structure and the effect of the proposed river training/control works on the same.

4.5. Other Data

  1. The extent of land available beyond the deep channel banks on both upstream and downstream within the reach shown on site plan together with details as to whether land is vacant, cultivated, etc.
  2. Availability of borrow-pit facilities, type and characteristics of local7

    soil, stone quarry having 40 kg (or 300 mm size) boulders and other materials suited for river training and control works.

  3. Need for plying of tippers on the top of guide bunds.
  4. Availability of local labour and machines for construction and maintenance works.
  5. Aerial photographs or maps for different years to study the meandering characteristics of the stream.
  6. Rate of aggradation for streams in sub-montane regions.

4.6. Design Data

4.6.1. Discharge:

The design discharge for which the river training works are to be designed shall be in accordance with the recommendations of IRC: 5-1985 “Standard Specifications and Code of Practice for Road Bridges, Section I, General Features of Design (Sixth Revision)”.

4.6.2. Scour depth:

The mean depth of scour (dsm) below the highest flood level, shall be calculated in accordance with provisions of IRC:5.

4.6.3. Afflux:

Afflux shall be calculated as per formula given in Appendix 1 (a).

For bridges across rivers carrying discharges more than 3000 m3/sec., afflux shall be calculated as per the method given in Appendix 1 (b) also and a reasonable value adopted.

5. GUIDE BUNDS

5.1.

The provisions given hereunder apply only to guide bunds for bridges across alluvial rivers. Guide bunds for bridges across sub-montane rivers need special consideration which are discussed in para 9.8

5.2. General Design Features

5.2.1. Alignment:

The alignment shall be such that the pattern of flow remains as uniform through all the spans of the bridge as may be possible with minimum return currents.

5.2.1.1. Alignment of approach embankment:

The alignment of approach embankment should be so chosen that it is not affected by the worst possible embayment which is influenced by the length of guide bunds. In general these are aligned in line with the axis of bridge upto high defined banks. In case the alignment of road has to be given a curve before reaching the high defined banks, it has to be provided towards the downstream side and not towards upstream side.

5.2.2. Classification of guide bunds:

Guide bunds can be classified:

  1. according to their form in plan, and
  2. according to their geometrical shape.

5.2.2.1. According to form in plan:

The guide bunds can be divergent, convergent and parallel, Fig. 5.1.

  1. Divergent guide bunds: They exercise an attracting influence on flow and they may be used where the river has already formed a loop and the approaching flow has become oblique. However, they have a tendency of shoal formation at centre due to larger waterway between the curved heads. The approach embankment gets comparatively lesser protection in the case of worst possible embayment compared to equal bank length of parallel guide bunds, Fig. 5.2. Divergent guide bunds, therefore, require a longer length in comparison to parallel guide bunds for the same degree of protection to approach embankments and so, shall be used, only when found necessary.
  2. Convergent guide bunds: Convergent guide bunds have disadvantage of excessive attack and heavy scour at the head and shoaling all along the shank, rendering the end bays inactive. These should be avoided as far as possible.9

    Fig. 5.1. Different forms of guide bunds (Para 5.2.2.1)

    Fig. 5.1. Different forms of guide bunds (Para 5.2.2.1)10

    Fig. 5.2. Extent of protection provided by parallel and divergent guide bunds [Para 5.2.2.1 (i)]

    Fig. 5.2. Extent of protection provided by parallel and divergent guide bunds
    [Para 5.2.2.1 (i)]

  3. Parallel guide bunds: Parallel guide bunds with suitable curved heads have been found to give uniform flow from the head of the guide bund to the axis of the bridge and so these are generally preferred.
5.2.2.2. According to geometrical shape:

Guide bunds can be straight or elliptical with a circular or multi radii curved head, Fig. 5.3. In case of acute curved channel approaches, it has been found that the flow after striking the mole head does not follow the profile of parallel guide bunds with circular heads but separates from the boundary as illustrated in, Fig. 5.4. It results in an oblique approach of flow to the bridge thereby making some of the end spans completely ineffective while increasing the intensity of flow in the remaining bays. To improve the flow conditions the provision of elliptical guide bunds is suggested. The ratio of major to minor axis is generally kept in the range of 2 to 3.5. Elliptical guide bunds have generally been found more suitable in case of wide flood plain/ rivers as compared to straight guide bunds.11

Fig. 5.3. Geometrical shape of guide bunds (Para 5.2.2.2)

Fig. 5.3. Geometrical shape of guide bunds
(Para 5.2.2.2)12

Fig. 5.4. (a) Straight guide bund with circular head (b) Elliptical guide bund followed by circular ARC (Para 5.2.2.2.)

Fig. 5.4. (a) Straight guide bund with circular head
(b) Elliptical guide bund followed by circular ARC (Para 5.2.2.2.)13

5.2.2.3.

Any other type of guide bunds differing in form or shape may be provided,' warranted by site conditions and supported by the model studies.

5.2.3. Length of guide bunds on upstream side

5.2.3.1.

For wide alluvial belt, the length of guide bund should be decided from two important considerations, namely the maximum obliquity of the current and the permissible limit to which the main channel of the river can be allowed to flow near the approach embankment in the event of river developing excessive embayment behind the guide bunds.

5.2.3.2.

The radius of the sharpest loop should be ascertained from the data of the acute loops formed by the river during the past. If survey plans do not reveal the presence of a sharpest loop, it may be calculated as follows:

Of available loops (Fig. 5.5.) calculate radius (r) of each at centre line by formula.

Fig. 5.5. Sketch showing a loop in a river (Para 5.2.3.2.)

Fig. 5.5. Sketch showing a loop in a river (Para 5.2.3.2.)

Notations:

mi = Meander Length
mb = Meander Belt
b = Average width of channel during floods14

Image

where r1 = radius of loop in metre
m1 = meander length in metre
mb = meander belt in metre
b = average width of channel during floods in metre

From the above, calculate the average radius of the loop. This average radius divided by 2.5 for rivers having maximum discharge upto 5000 m3/ sec. and by 2.0 for maximum discharge above 5000 m3/sec. gives radius of the sharpest loop. After having determined the radius of the sharpest loop, the single or double loop are laid out on survey plan that contains the alignment of approach embankments and high banks and it may be ensured that the safe distance between the anticipated sharpest loop and approach embankment is not less than L/3 where L is the length of the bridge. However, specially in the case of meandering rivers, this safe distance may be suitably increased.

5.2.3.3.

The length of guide bund on the upstream side is normally kept as 1.0 L to 1.5 L where no model studies are carried out. For elliptical guide bund the upstream length (semi major axis al) is generally kept as 1.0 L or 1.25 L.

5.2.3.4.

Guide bunds will generally not be able to protect the approach bank within the Khadir for more than three times its lengths, as evolved above, beyond the abutments on the upstream side. Where approach banks are more than three times the length of guide bunds, additional training/ protective measures may be necessary to protect the approach banks.

5.2.4. Length of guide bund on downstream side:

On downstream side of the structure, the river tries to fan out to regain its natural width. Here the function of guide bund is to ensure that the river does not attack approach embankments. Length equal to 0.2 L is generally found to be adequate. In special situations, the length may have to be suitably increased or decreased depending upon the circumstances.15

5.2.5. Curved head and tail for straight guide bunds

5.2.5.1.

Function of curved head is to guide river flow smoothly and axially through the bridge keeping the end spans active. A too small radius gives a kick to the river current making it oblique and so larger radius to attract and guide the river flow is needed. However, as it is uneconomical to provide a very large radius, it may be kept as small as possible consistent with proper functioning of guide bund.

5.2.5.2.

Radius of upstream mole head may be kept 0.4 to 0.5 times the length of the bridge between abutments, but it should not be less than 150 m nor more than 600 m unless indicated otherwise by model studies.

5.2.5.3.

Radius of curved tail may be from 0.3 to 0.5 times the radius of upstream mole head.

5.2.5.4. Sweep angle:

The angle of sweep of the upstream mole head is kept 120° to 140° and that for the curved tail is kept 30° to 60°.

5.2.6. Curved head for elliptical guide bunds:

In case of elliptical guide bunds, the elliptical curve is provided upto the quadrant of an ellipse and is followed by multi-radii or single radius circular curve, Fig. 5.3. The shape should be finalised preferably on the basis of model studies.

5.2.7.

For guide bunds of bridges across major rivers, hydraulic model studies are recommended for deciding the various design features.

5.3. Design of Guide Bund

5.3.1. Top width:

The top width of guide bunds for bridges across major rivers is generally kept at least 6 metre to permit passage of vehicles for carriage of materials.

5.3.2. Free board:

The free board should be measured from the pond level behind the guide bund after taking into consideration the afflux, kinetic energy head and water slope.16

5.3.2.1.

The minimum free board to top of guide bund above the pond level is generally kept as 1.5 m to 1.8 m. This may be suitably increased in the case of guide bunds for bridges across major rivers. The top of guide bund should follow the slope of river flow.

5.3.2.2.

In case where model studies are conducted for guide bunds, the model studies will also indicate the highest anticipated pond level immediately behind the guide bunds and at suitable intervals along the approaches, wherever, significant ponding up is anticipated.

5.3.2.3.

In cases where rivers have aggrading tendencies i.e. deposition of silt/sand in bed over the years, suitable extra provision will have to be made while working out the pond level to allow for the effect of aggradation.

5.3.3. Side slope:

The side slope of the guide bunds may be determined from the consideration of slope stability of embankment and from hydraulic gradient considerations. Generally a side slope of 2 (H): 1 (V) is adopted for predominently cohesionless materials.

5.3.4. Slope protection:

The river side earthern slope of guide bunds are protected against river action by covering them with stones/concrete slabs. The pitching is intended to remain in its laid position. It should be extended upto the top of guide bund and tucked inside for a width of at least 0.6 m.

5.3.4.1.

Rear slopes of guide bunds are not subjected to direct attack of the river and may be protected against ordinary wave splashing by 0.3 - 0.6 m thick cover of clayey or silty earth and turfed. Where moderate to heavy wave action is expected slope pitching should be laid upto a height of 1 m above the pond level.

5.3.5. Pitching on the river side slope:

For the design of pitching on the river side, the factors to be taken into consideration are size/weight of the individual stone, its shape and gradation, thickness and slope of pitching and type of filter underneath. The predominant flow characteristic which effects the stability of the pitching is velocity along the guide bund. Other factors like obliquity of flow, eddy action, waves, etc. are17

indeterminate and may be accounted for by providing adequate margin of safety over the size obtained from velocity considerations.

5.3.5.1. Size and weight of stone for pitching:

The size of stone required on the sloping face of guide bunds to withstand erosive action of flow may be worked out from the following equation:

d = Kv2

where

K = 0.0282 for face slope of 2:1 and 0.0216 for face slope of 3:1

d = equivalent diameter of stone in metre

v = mean design velocity in metre/sec.

The weight of stone can be determined by assuming spherical stone having a specific gravity of 2.65 (average). Plot of size and weight of stone against velocity of flow for different face slopes are given in Fig 5.6. For velocities upto 5 m/sec., the size and weight of stone is also given in Table 5.1.

Table 5.1
Mean design velocity m/sec. Minimum size and weight of stone
Slope 2:1 Slope 3:1
Diameter (cm) Weight (kg) Diameter (cm) Weight (kg)
Upto 2.5 30 40 30 40
3.0 30 40 30 40
3.5 35 59 30 40
4.0 45 126 35 59
4.5 57 257 44 118
5.0 71 497 54 218

Notes:

  1. No stone weighing less than 40 kg shall, however, be used.
  2. Where the required size stones are not economically available, cement concrete blocks or stones in wire crates may be used in place of isolated stones of equivalent weight. Cement concrete blocks will be preferred wherever practicable.
  3. For slopes between 2:1 and 3:1, the value of 'K' in the formula above can be interpolated linearly.
  4. Weighted spherical dia of stone should not be less than 200 mm while using wire mesh crates.18

Fig. 5.6. Size of stone pitching v/s velocity (Para 5.3.5.1)

Fig. 5.6. Size of stone pitching v/s velocity (Para 5.3.5.1)19

5.3.5.2. Thickness of pitching:

The thickness of pitching (t) may be determined from the following formula:

t = 0.06 Q1/3

where Q = design discharge in m3/sec.

The thickness of stone pitching computed from the above formula shall be subject to an upper limit of 1.0 m and a lower limit of 0.3 m. The thickness of pitching may be suitably increased in case of guide bunds of bridges across major rivers.

For the stones in wire crate the thickness of pitching (t) may be determined from the following formula:

Image

Where S2 = Specific gravity of stone normally taken as 2.65

However, while working out size of wire crate as per Appendix-2 the mass specific gravity (Sm) and porosity (c) can be worked out using following relationship

Image

Where d50 = Mean diameter of stones used in crate in millimeters

5.3.5.3. Shape of stones:

Quarry stone is preferable to round boulders as the latter roll off easily. Angular stones fit into each other better and have good interlocking characteristics.

5.3.5.4. Placing of stones:

In hand placed pitching, the stone of flat stratified nature should be placed with the principal bedding plane normal to the slope. The pattern of laying shall be such that the joints are broken and voids are minimum by packing with spalls wherever necessary and the top surface is as smooth as possible. In the case of guide bunds for bridges across major rivers, stone masonry bands may be provided at suitable intervals if considered necessary.

5.3.6. Filter design

5.3.6.1.

Filter shall consist of sound gravel, stone, jhama (overbumt) brick ballast and coarse sand. Now a days in other countries geotextiles are also being used as filter material. But, in India these have not been used extensively. As such these may be used only after considering their cost effectiveness and under expert guidance.

5.3.6.2.

Provision of a suitably designed filter is necessary under the slope pitching to prevent the escape of underlying embankment material through the voids of stone pitching/cement concrete slabs as well as to allow free movement of water without creating any uplift head on the pitching when subjected to the attack of flowing20

water and wave action, etc. In order to achieve this requirement, the filter may be provided in one or more layers satisfying the following criteria:

Image

Notes:

  1. Filter design may not be required if embankment consists of CH or CL soils with liquid limit greater than 30 resistant to surface erosion. In this case, if a layer of material is used as bedding for pitching, it shall be well graded and its D 85 size shall be at least twice the maximum void size in pitching.
  2. In the foregoing D 15 means the size of that sieve which allows 15 per cent by weight of the filter material to pass through it and similar is the meaning of D 50 and D 85.
  3. If more than one filter layer is required, the same requirement as above shall be followed for each layer. The finer filter shall be considered as base material for selection of coarser filter.
  4. Where brick bats are used as filter material, normally the grading is not possible and in such cases, a layer of graded gravel shall be provided below the brick bats.
  5. The filter shall be compacted firmly. The thickness of filter is generally of the order of 200 mm to 300 mm. Where filter is provided in two layers, thickness of each layer shall be 150 mm.

5.3.7. Toe protection

5.3.7.1.

Launching apron shall be provided for the protection of toe and it shall form a continuous flexible cover over the slope of the possible scour hole in continuation of pitching upto the point of deepest scour. The stone in the apron shall be designed to launch along the slope of the21

scour hole so as to provide a strong layer that may prevent further scooping out of river bed material. The size and shape of apron depends upon the size of stone, thickness of launched apron, the depth of scour and the slope of launched apron. At the junction of slope pitching with launching apron, a toe wall shall be provided as shown in Fig. 5.7, so that pitching does not rest directly on the apron. It will protect the slope pitching from falling during the launching of apron even when the apron is not laid at low water level.

Fig. 5.7. Sketch showing toe wall at junction of slope pitching and launching apron (Para 5.3.7.1.)

Fig. 5.7. Sketch showing toe wall at junction of slope pitching and launching apron
(Para 5.3.7.1.)

5.3.7.2. Size and weight of stone for apron:

The size of stone required for launching apron to resist mean design velocity (average velocity) is given by the formula:

Image

where

ϑ = mean design velocity in metre/sec

d = equivalent diameter of stone in metre

The weight of stone can be determined by assuming spherical stones having a specific gravity of 2.65 (average). Plot of size and weight of stone against velocity is given in Fig. 5.8.22

Fig. 5.8. Size of apron stone versus velocity (Para 5.3.7.2.)

Fig. 5.8. Size of apron stone versus velocity
(Para 5.3.7.2.)23

For velocities upto 5.0 m/sec., the size and weight of stone is also given in Table 5.2.

Table 5.2
Mean design velocity m/sec. Minimum size and weight of stone
Diameter (cm) Weight (kg)
upto 2.5 30 40
3.0 38 76
3.5 51 184
4.0 67 417
4.5 85 852
5.0 104 1561
Notes
  1. No stone weighing less than 40 kg shall be used for the apron.
  2. Where the required size stones are not economically available, cement concrete blocks or stones in wire crates or cementconcrete blocks and stones in wire crate in combination may be used in place of isolated stones of equivalent weight. Cement concrete blocks will be preferred wherever practicable.
5.3.7.3. Details of wire mesh crates: (see Appendix-2)

5.3.7.4. Depth of scour:

The extent of scour depends on angle of attack, discharge intensity, duration of flood and silt concentration. It is important that maximum probable depth of scour should be assessed as realistically as possible. The depth of scour for different portions of guide bunds may be adopted as under:

Location Maximum scour depth to be adopted
Upstream curved mole head of guide bund 2-2.5dsm
Straight reach of guide bund including tail on the downstream of guide bund 1.5dsm

Where dsm is the mean depth of scour.24

5.3.7.5. Shape and size of launching apron:

It has been observed that shallow and wide aprons launch evenly if the scour takes place rapidly. If the scour takes place gradual, the effect of width on launching of apron is marginal. A width of launching apron equal to 1.5 dmax is generally found satisfactory (where dmax is the maximum anticipated scour depth below bed level in meters). Thickness of launching apron at inner end may be kept as 1.5 t and at outer end 2.25 t as shown in Fig. 5.9.

When stones in wire crates are used the width of launching apron equal to 2.25 dmax for slope of 2:1 and 3.20 dmax for slope of 3:1 may be used. However, the thickness of launching apron may be kept same as that of thickness of pitching (t).

5.3.7.6. Slope of launching apron:

The slope of the launching apron may be taken as 2 (Η): 1 (V) for loose boulders or stones and 1.5 (Η): 1 (V) for cement concrete blocks or stones in wire crates.

5.3.7.7.

An apron may fail to provide protection to the guide bund if the river bed contains high percentage of silt or clay or where the angle of repose of the bed material is steeper than that of stone as in such a case the apron may not launch properly.

5.3.7.8.

Certain types of kankar blocks develop cementing action under water and such types of kankar blocks may be used with caution.

5.4. Constructional Aspects

5.4.1.

Co-ordination is necessary for tagging together guide bunds of road and rail bridges on the same river or streams where located in close vicinity of each other is likely to be influencing one or the other and for the same appropriate combined, if necessary, hydraulic model studies for both should be carried out to evolve properly tagging design.

5.4.2.

Trial pits should be taken in borrow area to examine suitability of soil for construction and also to decide the type of earth moving machinery to be arranged.

5.4.3.

Guide bunds may be made of locally available materials from the river bed preferably cohesionless materials. Low density cohesionless soils (loamy soils) are susceptible to liquifaction and should be avoided.

5.4.4.

Every effort should be made to complete the work of guide bund in one working season.25

Fig. 5.9. Details of guide bunds (Para 5.3.7.5)

Fig. 5.9. Details of guide bunds
(Para 5.3.7.5)26

5.4.5.

For the construction of embankments for guide bunds IRC: 36 “Recommended Practice for the Construction of Earth Embankments for Road Works’’ shall be followed unless otherwise stated in these guidelines. For high embankments IRC: 75 “Guidelines for the Design of High Embankments’’ may be followed.

5.4.6. Dispatch of stone:

Transport of stone from the quarries to the river bank and from the river bank to the site of work is an important task. The quantities of stone required to be transported every day must be worked out and trains/ trucks, etc., arranged accordingly. Similarly prior arrangements may be made for taking the stones across the river by ferry or boats.

5.4.7. Earthwork

5.4.7.1.

For construction of guide bunds, four operations are involved:

  1. excavation of the pit for the apron
  2. the completion of the earth work for guide bunds
  3. the construction of approach banks
  4. laying stones in apron and on slopes
5.4.7.2.

It is necessary that sufficient length of pit along the guide bund should be ready within one or two months of commencement of work so that placing of stones in the apron and on slope can be started at the earliest. About 70 per cent working season should be available for pitching. Earthwork should be completed within 80 per cent of working season. Good compaction of guide bunds is necessary as any slip during the flood can be disastrous. No portion of the guide bund should be left below HFL before the onset of monsoon. Bottom of apron pit should be excavated as low as permitted by water level.

5.4.7.3.

Sufficient labour and/or earth moving machinery of the right type with spare parts and trained staff is necessary.

5.4.7.4. Borrow pits:

No borrow pits should be dug on the rear of guide bunds. It is preferable to take all earth for construction of the guide bunds27

from the river side. The borrow pits should be sufficiently away from the location of the launching apron.

5.4.8.

Adequate labour for unloading of pitching stone, carrying and laying it at site within the time available will have to be carefully worked out.

5.4.9.

Construction of guide bunds should be taken in hand along with piers and abutments. Where there is any doubt about completion of whole guide bund within one working season, it is absolutely essential that the construction of guide bund be started from abutment towards upstream. Where full guide bund cannot be constructed in one working season suitable protective measures may be taken.

5.4.10.

On slopes, care should be taken in placing the stone not to have big voids through which water will cause swirling. Comparatively smaller stones should be at the bottom and larger ones at the top.

5.4.11.

The top of the guide bunds should be protected with a layer of 15 cm thick gravel against rain cuts.

5.4.12.

While on river side, stone protection is provided upto the full length of guide bunds, on the rear side this protection is just carried around mole head beyond which usually good turfing is provided.

5.4.13. Closure of branch channels of a river:

In case the alignment of guide bund or the approach embankment crosses a branch channel of the river, the usual practice under such circumstances is either to divert the branch channel to the main channel of the river with the help of spurs, etc., or to construct closing dyke or closure bund across the branch channel. In situations where diversion of channel is to be resorted to, then action in this regard should be taken during the receding floods and at least 2 to 3 months in advance of the construction of guide bund/ embankment. In situations where closing of the branch channel is considered unavoidable, then the closure bund closing dyke or the armouring of the approach embankment should be properly designed and closing operation should be carried out as a continuous one.28

6. SPURS

6.1. Functions of Spurs and their Classifications

6.1.1. Function of spurs

6.1.1.1.

Spurs are provided to take care of one or more of the following functions:

  1. Training the river along a desired course by attracting, deflecting or repelling the flow of a channel.
  2. Creating a slack flow with the object of silting up the area in the vicinity.
  3. Protecting the river bank by keeping the flow away from it.
  4. Contracting a wide river channel, usually for the improvement of depth for navigation.

6.1.2. Classification of spurs:

Spurs can be classified as follows:

  1. Classification according to method and materials of construction: Permeable and impermeable (solid).
  2. Classification according to the height of spur with respect to water level: Submersible or non-submersible.
  3. Classification according to the function served: Attracting, deflecting, repelling and sedimenting, Fig. 6.1.
  4. Special type-T-headed, Hockey or Burma type and kinked type, etc., Fig. 6.1.
6.1.2.1. Permeable spurs:

Permeable spurs obstruct flow and slacken it to cause deposition of sediment carried by the streams. These are, therefore, best suited for sediment carrying streams and are also preferable in hilly regions.

In comparatively clear rivers their action results in damping erosive effect of the current and thus prevent, local bank erosion.

6.1.2.2. Impermeable spurs (solid):

Impermeable spurs consist of rockfill or earth core armoured with resistant material like stone mattress29

Fig. 6.1. Types of spurs or groynes (Para 6.1.2. (iii) & (iv))

Fig. 6.1. Types of spurs or groynes (Para 6.1.2. (iii) & (iv))

or sausages filled with stone. They are designed to attract, repel or deflect the flow away from the bank along a desired course.

6.1.2.3. Submersible spur:

A submersible spur is the one whose top level is above the normal water level in the river but gets submerged during the highest design floods.

6.1.2.4. Non-submersible spur:

This is the type of spur which remains above water even under the highest floods.30

6.1.2.5. Attracting spur:

These are the spurs which attract flow towards the bank and are aligned in a direction pointing downstream. In a river where there is a heavy attack on one bank, it may be desirable to construct the attracting spurs on the opposite bank in conjunction with a repelling spur on the affected bank.

6.1.2.6. Repelling spur:

A spur pointing upstream has the property of repelling the river flow away from it and hence it is termed as repelling spur.

6.1.2.7. Deflecting spur:

Where the spur, usually of short length changes only the direction of flow without repelling it, is known as a deflecting spur and gives only local protection.

6.1.2.8. Sedimenting spur:

The spurs located at right angles to the river flow fall under this category.

6.1.2.9. Special type spur:

These spurs have been named after their builders and have special design features like Denhey’s T Headed, Hockey or Burma type and kinked type, etc. A spur with a curved head is known as a Hockey or Burma type spur whereas a spur with a short straight head normal to spur direction is known as a Denhey’s T Headed spur and a spur with a slight angular head is known as a kinked type spur.

6.2. General Features

6.2.1. Location and length:

No general rule can be laid for fixing the length and location of the spurs. Those depend entirely upon the exigencies arising in a specific case. Length should not be shorter than that required to keep the scour hole formed at the nose away from the bank. Short length may also cause bank erosion upstream of the spur whereas too long a spur may dam up the river. Normally spur should not obstruct more than 20 per cent of the channel width at ordinary flood level.

6.2.2. Orientation:

For repelling spur (defined in clause 6.1.2.6) the angle upstream varies from 60° to 80° with the bank. In the case of attracting spur (defined in clause 6.1.2.5) the angle is usually 60° (within a range of 30° to 60° with the bank. Orientation for deflecting spur (defined in clause 6.1.2.7) can vary from 65° to 85°.31

6.2.3. Spacing:

In a straight reach the spacing is about three times the length of spur. Spurs are spaced further apart (with respect to their length) in a wide river than in a narrow one, if their discharges are nearly equal. In a curved reach a spacing of 2 to 3.5 times the length of spur is recommended. Larger spacing (3 to 3.5 times) can be adopted for concave banks and smaller spacings (2 to 3 times) can be adopted for convex banks. Sometimes the spurs are spaced further apart from consideration of cost or for enabling construction of more spurs at a later date.

6.2.4.

Location, length, orientation and spacing can best be finalized from model tests.

6.3. Design of Impermeable Spurs

6.3.1. Top width:

The top width of spur should be 3 to 6 m at formation level.

6.3.2. Free board:

The minimum free board above the recorded highest flood level (H.F.L.) or above the anticipated H.F.L. on the upstream of spur, whichever is more is generally kept as 1.5 to 1.8 m.

6.3.3. Side slopes:

For cohesionless soils, slopes on upstream and downstream faces of 2 (Η): 1 (V) may be adequate. For spurs constructed wholly in stones steeper slopes may be adopted.

6.3.4. Size and weight of stone for pitching:

Same as for guide bunds (see para 5.3.5.1).

6.3.5. Thickness of pitching:

Same as for guide bunds (see para 5.3.5.2).

The thickness ‘t’ of the pitching should be provided in a length of 30 to 45m or for such a length of upstream shank upto which the river action prevails (whichever is more) and the semi-circular nose. In the next 30m to 60m the thickness of pitching may be reduced to 2/3t on upstream and in rest of the shank length 0.3 m thick stone pitching may be provided. On the downstream the thickness of pitching may be reduced to 2/3t in 30 m to 60 m and in rest of the shank length a nominal stone pitching or turfing may be provided.32

6.3.6. Filter:

A graded filter 20 cm to 30 cm in thickness generally satisfying the criteria mentioned in guide bunds (see para 5.3.6) should be provided below the pitching at nose and on the upstream face in a length of 30 to 45 m. In the next 30 to 60 m of the upstream shank portion the filter can be reduced to 15 cm and then filter may be eliminated.

6.3.7. Launching apron

6.3.7.1. Size and weight of stone:

Same as for guide bunds (see para 5.3.7.2).

6.3.7.2.

The depth of scour for different portions of spur can be adopted as given in Table 6.1 and shown in Fig. 6.2.

Table 6.1. Depth of Scour
S.No. Location Maximum scour depth to be adopted
(i) Nose 2.0 dsm to 2.5 dsm
(ii) Transition from nose to shank and first 30 to 60 m in upstream 1.5dsm
(iii) Next 30 to 60 m in upstream

1.27 dsm

(iv) Transition from nose to shank and first 15 to 30 m on downstream 1.27 dsm

Where dsm is the mean depth of scour measured below highest flood level (HFL)

Fig. 6.2. Plan showing depth of scour for spurs (Para 6.3.7.2)

Fig. 6.2. Plan showing depth of scour for spurs (Para 6.3.7.2)33

6.3.7.3. Shape and size of launching apron:

A width of launching apron equal to 1.5 dmax (where dmax is the maximum anticipated scour depth below low water level in metres) should be provided at semi-circular nose and should continue upto 60 to 90 m on the upstream or for such a length of upstream shank upto which the river action prevails (whichever is more). In the next 30 to 60 m on the upstream the width of launching apron may be reduced to 1.0 dmax. In the remaining reach, nominal apron or no apron may be provided depending upon the flow conditions. The width of the launching apron on the downstream should be reduced from 1.5 dmax to 1.0 dmax in 15 to 30 m and should continue in next 15 to 30 m. If the return flow prevails beyond the above specified reaches, the apron length may be increased to cover the region of return flow. Thickness of launching apron at inner end may be kept as 1.5 t and at outer end as 2.25 t. A typical design of spur is illustrated in Fig.6.3.

6.3.7.4. Slope of launched apron:

Same as for Guide Bunds (see para 5.3.7.6).

6.3.8.

Alternatively, spurs can also be designed with the help of polar diagrams discussed in para 8.

6.4. Permeable Spurs

6.4.1. Tree spurs:

The objects of the tree spurs are to:

  1. Divert or deflect the current which is directly threatening erosion of a bund;
  2. Deaden the flow in one channel of the river near the bund in order to open out another channel away from the bund; and
  3. Silt up a channel of the river at its source by checking the flow in it.
6.4.1.1.

Initially, the tree spurs should be laid pointing upstream at an angle between 60° to 70° so that when the spur launches and becomes sand bound, it assumes a position facing slightly upstream. Unlike an impermeable spur, which is generally made to face 60° upstream, a permeable spur should make a larger angle with the bank upstream, since it would collect floating debris against the face, converting it to an almost34

Fig. 6.3. Typical design of spur (Para 6.3.7.3.)

Fig. 6.3. Typical design of spur (Para 6.3.7.3.)35

impermeable one with attendant disadvantages. Care should be taken that after launching, it is not bodily shifted to assume a position of an attracting spur, which would induce accretion only downstream of it.

6.4.1.2.

Tree spurs consist of a thick wire rope firmly tied at one end to the bank and tied at the other end to a heavy concrete block. Leafy trees with large branches are suspended from the wire rope. Alternatively, the tree spurs are also constructed as detailed below:

Vertical stakes are driven 1.5 to 2.5 m into the river bed at 3 m intervals along the cross section of river (see Fig. 6.4). Each row of such stakes are placed about 9 m apart. These stakes are held in position by diagonal stays and guy ropes secured to strong pegs well embedded in the firm banks. The verticals (stakes) are connected to each other by transverse pieces having holes drilled in them to take the tapered end of intermediate verticals of 75. to 100 mm dia, placed in between the main verticals at 0.3 m centres. The entire structure is made watertight by lining the vertical stakes on their upstream side by bundles of local grass and the space between two such rows of spurs is thickly filled with trees. Holes are drilled 0.3 m up their stem through which a ring is fitted. The trees are held in position by a wire rope 2.5 cm dia attached to the rings, the wire rope being firmly anchored to the bank.

6.4.1.3.

However, generally tree spurs are cumbersome to construct and have not been found successful except in a few cases.

6.4.2. Pile spurs:

Spurs of this type can be constructed out of timber, sheet piles or even R.C.C. piles. In pile spurs (see Fig. 6.5) the piles constitute the main verticals: they are driven down 6 to 9 m inside the river bed, 2.4 to 3.0 m apart and in at least 2 similar rows. The rows of verticals are not more than 1.2 to 1.8 m apart. Between the main verticals, there can be two intermediates, embedded at least 1.2 m below the bed. Each row is either closely inter-twined with brush wood branches, going in and out around each vertical or horizontal railings. The upstream row is braced back to the downstream row by transverses and diagonals. Every other main vertical of the rear row has to be strutted. The strut being embedded a minimum of 2.4 m below bed. Betweeen the two rows, the36

Fig. 6.4. Tree spurs (Para 6.4.1.2.)

Fig. 6.4. Tree spurs (Para 6.4.1.2.)37

Fig. 6.5. Pile spurs (Para 6.4.2.)

Fig. 6.5. Pile spurs (Para 6.4.2.)38

space is filled with brush-wood branches, closely packed and tamped. The filling may comprise alternate layers of 1.8 m thick brush wood weighted down by 0.6 m thick stones and sand bags. However, debris collects upstream and the spur becomes sand bound and functions subsequently, like and impermeable spur. To guard against scour occurring under such conditions, it is desirable to protect the bed, both up-stream and downstream of the spur and around the nose with a stone apron, 0.9 m thick, 3 m wide along the shank and 6 m wide around nose.

7. RIVER BANK PROTECTION

Normally river bank protection is the prime responsibility of flood control authorities. However, for protection of a road embankment running along a river course or for protection of bridge abutment close to the river edge, bank protection measures are sometimes required to be adopted.

7.1. Causes of Bank Failure

For the purpose of design of bank protection, the causes of bank failure have first to be identified as listed below:

  1. Washing away of soil particles from the bank by a strong current
  2. Undermining the toe of the bank by eddies, currents, etc., followed by a collapse of overhanging material deprived of support
  3. Sloughing of slope when saturated with water by floods of long duration,
  4. Piping in sublayers due to movement of ground water towards the river which carries away material with it.

7.2. Type of Protection Work

7.2.1. Indirect method:

Spurs, porcupines, bed bars and studs/ dampeners.

7.2.1.1. Spurs:

These have been discussed in great detail in Chapter 6.39

7.2.1.2. Porcupines:

These are one particular type of permeable groynes which help to induce siltation along the banks. These are made of steel, bamboo or timber and are provided on a scouring bank in a line normal to the flow. These spurs increase the roughness of the channel thereby deflecting the eroding current away from the bank. In course of time, vegetation grows within the jacks and action of spur is enhanced further.

One type of porcupine, known as Kellner Jack comprises three steel angles about 5 m long bolted together at the centre with the wire string between the legs. A typical unit of porcupine looking from the bank is shown in Fig. 7.1 (a).

Other type of porcupine used for similar purpose is made of bamboo. These are made of 3 to 6 m long bamboo of 75 mm diameter tied together at the centre in the form of a space angle and are weighed down by tying boulder stones packed in wire cage at the centre. A typical bamboo type porcupine spur is shown in Fig.7.1 (b).

7.2.1.3. Bed Bars:

Bed bars are submerged structures which help to divide the flow horizontally. Flow above the top of the bed bars can be compared to flow over the submerged weir while flow below the top level of the bar is obstructed by it and is directed towards the nose as in the case of a full height spur. When the alignment of a bed bar is skewed, a pressure gradient is set up. The bed bars can be placed either facing towards upstream of the direction of flow or facing towards downstream of the flow direction.

When the bed bar is facing towards upstream of the flow, the pressure gradient developed helps to deposit sediment on the upstream side of the bar and thus is useful for bank protection. This is shown in Fig. 7.2(a).

When the bed bar is facing towards downstream of the flow, the pressure gradient directs the bottom current away from the bank while surface flow is directed towards the bank. This is provided upstream of an offtake point for sediment exclusion and is shown in Fig. 7.2(b).40

Fig. 7.1 (a): Steel Jetty-Kellner Jack

Fig. 7.1 (a): Steel Jetty-Kellner Jack

Fig. 7.1. (b): Porcupine spur (Para 7.2.1.2.)

Fig. 7.1. (b): Porcupine spur (Para 7.2.1.2.)41

Fig. 7.2 (a): Upstream facing bed bar

Fig. 7.2 (a): Upstream facing bed bar

Fig. 7.2 (b): Downstream facing bed bar (Para 7.2.1.3.)

Fig. 7.2 (b): Downstream facing bed bar (Para 7.2.1.3.)42

7.2.1.4. Studs:

These are short spurs provided between the regular long spurs to provide local protection to the river bank. Thus the studs are useful device of bank protection where embayments occur between the T-head groynes. A typical design of stud is given in Fig. 7.3.

7.2.2. Direct method:

Stone or concrete block revetment with properly designed launching apron.

7.3.

Before undertaking the work of permanent river bank protection, some sort of temporary protection work must be done near the abutments of the bridges located on the downstream. Only after observing the behaviour of the river for sometimes permanent river bank protection works should be taken up.

7.4. Design of Bank Protection

7.4.1. Grading:

Trees, brushwood, grass, etc., have to be removed both above and below the water level for clearing the bank. The cleared bank slope has then to be graded so that it is flatter or at least equal to the angle of repose of the soil under water so as to prevent sloughing. The landside slope of the pitched bank made in the form of an embankment should be flat enough to be stable. The top width of the embankment may be at least 1.5 m.

7.4.2. Free board:

A minimum free board of 1.5 m above HFL is generally provided.

7.4.3. Pitching:

Same as for guide bunds (see para 5.3.5).

7.4.4. Filter material:

Same as for guide bunds (see para 5.3.6).

7.4.5. Apron:

As the attracting influence of the pitched bank depends on the extent to which scour occurs at its toe, the revetment has to be provided with elaborate toe protection in the form of launching apron. The apron has to be designed for the maximum depth of scour likely to occur. Generally, the maximum anticipated depth of scour is assumed to be 1.5 dsm in a straight reach and at a moderate bend where dsm is the mean depth43

Fig. 7.3. Typical design of stud (Para 7.2.1.4)

Fig. 7.3. Typical design of stud (Para 7.2.1.4)44

of scour measured below highest flood level to be calculated as per IRC: 5. In the case of bank at severe bend, it is assumed as 1.75 dsm and in the case of bank at right angled bend, it is assumed as 2.00 dsm. The design of launching apron should be made in the same way as for guide bunds (see para 5.3.7.1.).

8. APPROACH ROAD PROTECTION

8.1. Different Categories of Approaches to Bridges - Protection Thereof

Nature of protection to be provided for approach embankment of highway bridges depends upon its location which can be divided into the following broad categories:

  1. Approach embankments subjected to flooding but where the velocity of flow is insignificant (not exceeding 1 m/sec.) to cause erosion.
  2. Approach embankments which are under direct and frontal attack of the river flow or otherwise subjected to velocity of flow exceeding 1 m/sec.
  3. Approaches to bridges located in the beds of meandering rivers with large khadir width requiring guide bunds, etc.

8.2. Approach Embankments subjected to Flooding but where the Velocity of Flow is Insignificant (not exceeding 1 m/sec.) to Cause Erosion

8.2.1.

These cases occur where the river flows through flat terrain with large spills. In such cases, bridges have to be provided with adequate waterway to allow for quick and easy flow of the flood water so as to prevent undue afflux and consequent submergence of valuable agricultural and other lands. Further where the bed material is scourable, flooring with curtain walls is often provided. In case spill-through type abutments are provided in conjunction with the flooring, the sloping embankments in front of the abutments, often extending into the river causing some construction in the flow, need to be adequately protected against the erosive attack of the flow across the embankment.45

8.2.1.1.

Apart from the above, cases may also arise wherein spill-through type abutments may be adopted from economic consideration for bridges with open foundations in non-scourable or rocky bed. In such cases also, the approaches will need to be adequately protected. In either case, the treatment should be on the lines discussed in para 8.2.2.

8.2.2.

For a particular bank slope and velocity of flow, the thickness of the slope pitching, size of the stone, its gradation and filter design should be worked out in accordance with the recommendations made in para 5.3. However, the designed values arrived at should not fall below those indicated in Figs. 8.1(A) or 8.1(B).

8.2.2.1.

The slope pitching should terminate either in a short apron at the bed level as indicated in Fig. 8.1(A) or the pitched slope anchored in the flooring/rock as shown in Fig.8.1 (B). However, along the length of the approach, the bank protection should begin and end at a stable section on the approach subject to a minimum of 15 m. In cases where the river banks have to be protected they should also be protected in a similar manner and if such stable sections are not available, suitable terminal treatment of pitching should be provided at the ends as shown in Fig.8.2.

8.3. Approach Embankments which are under Direct and Frontal attack of the River or otherwise subjected to velocity of flow exceeding 1 m/sec.

8.3.1.

These cases occur where the flow is confined within banks during ordinary floods but spills during high floods without meandering. In such cases, waterways provided are often less than the bank to bank width of the river, which is very wide during high floods and the approaches to the bridges protrude into the river tending to act like spurs. There will be parallel flow with increase in velocity along the embankment. The distance of the embankment so affected depends directly upon the percentage of constriction adopted and the angle of crossing. Large constrictions will not only result in excessive cost of protection consequent to deepening of bed but would also entail deeper foundation of bridges, as well as change in channel profile both upstream and downstream. The final decision as to the percentage of constriction to be adopted should46

Fig. 8.1. Typical sections of stone slope protection (Para 8.2.2)

Fig. 8.1. Typical sections of stone slope protection (Para 8.2.2)

Fig. 8.2. Details of cut-off at terminals of rip-rap blanket (Para 8.2.2.1)

Fig. 8.2. Details of cut-off at terminals of rip-rap blanket (Para 8.2.2.1)47

be such that the cost of the bridge plus the protection to be provided is the minimum. The various parameters that affect the design of protective works of the approaches are as under:

  1. Intensity of discharge
  2. Angle of crossing
  3. Velocity of flow
  4. Scour pattern around the approaches; and
  5. Soil in the embankment fill.

8.3.2.

Under the above conditions, the approach embankment protruding into the river is under the direct attack of the river flow and this needs to be protected like a spur. It is seen that the scour reduces as one moves along the spur towards the bank for which the extent of protection could be curtailed towards the bank. The polar diagrams given in Fig. 8.3 show the centre line of spur as base and the ratio of deepest scour depth to mean depth of scour as ordinates. These ratios can be made use of to ascertain the maximum scour depth once the mean depth of scour is known. Thereafter, once the points of deepest scour are known, the apron widths for the approach embankments can be designed in accordance with the provisions contained in para 5.3.

8.3.3.

Another aspect is the length along the approach embankments which needs to be protected. The length on the upstream and downstream side of the spurs needing protection bears a linear relationship with the angle of spur as shown in Fig. 8.4. On the analogy of the approach embankments acting as short spurs, the upstream and downstream lengths needing protection may be divided into two categories as shown in Fig. 8.3 viz., category ‘X’ extending from the bank to the point of mean depth of scour and category Ύ’ extending from the point of mean depth of scour to the point of deepest scour towards the deep channel. The portion covered under category ‘Y’ could be assessed based on the corresponding values of the lengths of spurs requiring to be protected, i.e., ‘Lx’ given as fraction of total length ‘L1’ of approach embankment projecting into the river and obtained by taking the angle of spur to the direction of flow and reading the values from Fig. 8.4. The length of the approach L1-Lx gives the length of the approach under category ‘X’. Design of the slope pitching, filter backing and apron under category ‘X’ and category ‘Y’48

Fig. 8.3. Polar diagram of different inclination of a straight spur showing type and extent of projection (Para 8.3.2.)

Fig. 8.3. Polar diagram of different inclination of a straight spur showing type and extent of projection (Para 8.3.2.)

could be made on the basis of recommendations given in para 5.3. The apron width for category ‘X’ may be designed as a nominal one and its width reduced uniformly from that required at the end of category ‘Y’ to 2.5 m (minimum).49

Fig. 8.4. Length requiring protection as a function of the spur inclination (Para 8.3.3.)

Fig. 8.4. Length requiring protection as a function of the spur inclination (Para 8.3.3.)

8.4. Approaches to Bridges located in the Beds of Meandering Rivers with large Khadir width requiring Guide Bunds, etc.

8.4.1.

These cases pertain to rivers which meander in the alluvial plains and have large Khadir widths even under ordinary flood conditions. From economic considerations, it is, however, imperative to provide waterways much less than the width between ends of the Khadir of the river. This is achieved with the help of guide bunds, the treatment of which has been discussed in para 5, which restrict the river to flow within an artificial gorge. The section of the approach embankment beyond the Khadir portion is subjected to flooding but there is no significant flow to cause scour due to parallel flow or draw down conditions and balancing of water on both sides of the embankment. For these conditions to be satisfied, however, the alignment of the approach embankment and its distance from the worst possible embayment loop should be fixed as indicated in paras 5.2.1.1 and 5.2.3.1 respectively.

8.4.2.

In view of still water conditions, nominal slope pitching, e.g., 0.3 m thick may be provided for embankment height upto 7.5 m increased to 0.5 m in the lower portion where its height exceeds 7.5 m. The minimum weight of stones used shall be 40 kg.

8.4.3.

The design of filter backing is dependent on the voids in the stone pitching and the gradation of bank material. For the nominal nature of50

pitching suggested in the preceding sub-para, base filter of 150 mm thickness may do.

8.4.4.

The slope pitching should extend well above the pond level taking into account the exigencies of abnormal floods and wave action. The free board in any case, should not be less than 1.2 m. A higher free board would be advisable in case of aggrading rivers.

8.4.5.

The pitched slopes should be provided with nominal toe protection in view of very little velocity. At any rate, toe walls should be avoided and nominal apron of at least 2.50 m width and 0.50 m thickness should be provided at bed level. No protection of downstream slope is ordinarily necessary and provision of turfing may suffice.

In case other types of pitching and filter materials as well as toe protection measures are required to be adopted as per site conditions, a suitable design as recommended in para 5.3 may be adopted.

8.4.6.

For construction of approach embankments within the khadir area no borrow pits shall be permitted within the area bounded by the guide bund on one side, natural bank on the other side and the lines drawn tangentially to the top of upstream and downstream curved heads parallel to approach embankment. Moreover, the edge of the nearest borrow pits shall be not less than 200 metre from the toe of the embankment both on the upstream and downstream side in any case.

8.4.7.

As far as possible, no opening should be provided in the bridge approaches falling in the khadir portion of the river. However, if these are unavoidable, only floored structures should be provided with revetment in immediate approaches on either side of the structure. These structures should be provided with sluice gates which should be kept closed during flood season.

8.4.8.

Where the approach embankment in the Khadir terminates in a marginal bund or at any protective embankment/afflux bund constructed by irrigation/flood control department, the adequacy of the latter within the zone of influence of embayment should be checked and if need be, the same should be got suitably raised/strengthened in that stretch.51

8.5. Special Consideration

The aforesaid guidelines do not cover the provision where the approach embankments are under the attack of sea waves or tidal bores, etc. In such cases, the protective measures may be evolved based on expert literature/model experiments. Stability of embankments to be protected should be ensured on the basis of local experience and/or slope stability analysis related to appropriate soil data.

9. DESIGN OF RIVER TRAINING AND CONTROL WORKS IN SUB-MONTANE REGIONS

The rivers in sub-montane regions do not present a regular pattern of meanders as in the case of alluvial rivers in plains. The bed slopes of the rivers in the hilly regions are very steep which create tremendous velocities and bed materials being unable to withstand such velocities are scoured and transported down the river. They carry very heavy charge of coarse sand, shingle and boulders, which are accentuated by large slips and landslides that take place in the hill slopes and result in heaps of deposits on flatter slopes. In the North-Eastern part of this country, it is further aggravated by the seismic character of the Himalayan zone. Due to seismic disturbances the friable rock loosens and landslides occur and the sediment load of the Himalayan rivers increases substantially. The channels become shallow and owing to the reduced velocity, obstructions in the form of heaps result in diversion of the channel itself. As the river bed upstream through the bridge itself rises, the flood cannot pass through the bridge quickly and it heads up-above the bridge submerging low lying areas. The bed level of the river upstream of the bridge thus rises progressively with consequent rise in the flood levels resulting in increase in flooding of areas upstream of the bridge. The protection works for submontane regions merit special consideration besides the points already covered in earlier paras. It is, therefore, necessary that protection works for bridges in sub-montane regions are decided judiciously by the Engineer-in-charge keeping in view the site conditions and other relevant factors.

9.2.

Most of the rivers in sub-montane terrain are subject to the phenomenon of rolling boulders during high floods. Huge boulders hitting52

the piers and abutments may cause enormous damage. In such cases, heavy protection around piers/abutments may be necessary which may be in the form of stone facing or steel plate lining. The same may be decided by the Engineer-in-charge keeping in view the site conditions. In case heavy floating debris is anticipated, necessary traps may be provided to prevent the same from reaching the structure.

9.3.

Permeable spurs and toe walls with launching apron may also be considered for protection works.

10. FLOOR PROTECTION

10.1.

For bridges where adoption of shallow foundations becomes economical by restricting the scour floor protection to bridges has to be provided. The floor protection will comprise of rigid flooring with curtain walls and flexible apron so as to check scour, washing away or disturbance by piping action, etc. Usually performance of similar existing works is the best guide for finalizing the design of new works. However, the following minimum specification for floor protection shall at least be followed while designing new structures subject to the general stipulation that post protection works velocity under the structure does not exceed 2 m/s and the intensity of discharge is limited to 3 m3/m.

10.2. Suggested Specifications

10.2.1.

Excavation for laying foundation and protection works shall be carried out as per specifications under proper supervision. Before laying the foundation and protection works the excavated trench shall be thoroughly inspected by the Engineer-in-charge to ensure that:

  1. There are no loose pockets, unfilled depressions left in the trench.
  2. The soil at the founding level is properly compacted to true lines and level.
  3. All concrete and other elements are laid in dry bed.

10.2.2. Rigid flooring:

The rigid flooring shall be provided under the bridge and it shall extend for a distance of at least 3 m on upstream side and 5 m on down stream side of the bridge. However, in case the splayed53

wing walls of the structure are likely to be longer the flooring shall extend upto the line connecting the end of wing walls on either side of the bridge.

10.2.2.1.

The top of flooring shall be kept 300 mm below the lowest bed level.

10.2.2.2.

Flooring shall consist of 150 mm thick flat stone/bricks on edge in cement mortar 1:3 laid over 300 mm thick cement concrete M-15 grade laid over a layer of 150 mm thick cement concrete M-10 grade. Joints at suitable spacings (say 20 m) may be provided.

10.2.3. Curtain walls:

The rigid flooring shall be enclosed by curtain walls (tied to the wing walls) with a minimum depth below floor level of 2 m on upstream side and 2.5 m on downstream side. The curtain wall shall be in cement concrete M-10 grade/brick/stone masonry in cement mortar 1:3. The rigid flooring shall be continued over the top width or curtain walls.

10.2.4. Flexible apron

10.2.4.1.

Flexible apron 1 m thick comprising loose stone boulders (weighing not less than 40 Kg) shall be provided beyond the curtain walls for a minimum distance of 3 m on upstream side and 6 m on downstream side. Where required size stones are not economically available, cement concrete blocks or stones in wire crates may be used in place of isolated stones.

10.2.5.

Wherever scour is restricted by provision of flooring/flexible apron, the work of flooring/apron etc., should be simultaneously completed alongwith the work on foundations so that the foundation work completed and left to itself is not endangered.

11. MODEL STUDIES

11.1. Objects of Model Studies

The river has its own peculiarities depending on its size, load characteristics, the terrain through which it flows and the nature of the54

banks. Hence, each case is to be considered individually. In spite of our efforts to improve the design, we are still to go a long way before understanding the absolute truth of nature and till then one has to cater for unknown parameters with a factor of safety. It is here that model studies offer a handy tool at supplementing the work of designer and by providing an insight into conditions likely to obtain in the prototype.

11.2. Situations Warranting Model Studies

11.2.1.

River flow being a very complex phenomenon, eludes easy analysis in many cases. This is more so in the case of bridges on the alluvial rivers where normal river waterway is constricted. In some cases where the bridges are not located on the straight reaches or where it is required to study the effects of other structures viz., an existing bridge, a weir, a new dam or flood embankments or ghats along the river, it is not possible to visualise the river behaviour accurately in respect of flow pattern, discharge distribution, etc., after the construction of the structure. In all such cases, model studies will be helpful.

11.2.2.

In cases where the cost of a new bridge project or additional river training works for existing bridge is substantial, model studies are advisable. Model studies in such cases cost a very insignificant percentage of the total cost of project and have the added advantage of suggesting improvements which may sometimes lead to reduction in the cost of the structure.

11.2.3.

The importance of the bridge viz., its location on strategic routes or its proximity to major industrial complexes, towns, etc. is yet another consideration for resorting to model studies.

11.2.4.

In the situations warranting model studies mathematical model studies may also be carried out as per guidelines indicated in Appendix-3.

11.3. Design Aspects Requiring Model Studies

11.3.1.

Model studies may be required for one or more design aspects55

as mentioned below.

11.3.1.1. Selection of site and alignment:

Selection of suitable site and alignment of bridge in relation to river configuration and flow.

11.3.1.2. Waterway:

Adequacy of bridge waterway in relation to velocities, flow distribution, afflux and location of guide bunds.

11.3.1.3. Guide bunds
  1. Layout
  2. Length of upstream and downstream parts in relation to velocities and discharge distribution across the bridge and in relation to all possible conditions of approach of the river for safety of guide bunds. The radius of curvature of upstream mole head of guide bund to ensure smooth flow conditions.
  3. Water levels behind the guide bunds and along the approaches.
  4. Maximum scour level at suitable points along the length of guide bund.
11.3.1.4. River bank protection:

Works like spurs, bank pitching etc., required if any, upstream or downstream sides of the bridge.

11.3.1.5. Bridge piers:

Afflux at the bridge piers, scour around the piers and at the river bed and related protective measures.

11.3.1.6.

To study the effects of existing or future structures like dams, ghats, spurs, embankments, etc., on bridges.

11.4. Data Required for Model Studies

The following details including ground survey, hydraulic and sediment data are required for model studies.

11.4.1. Report:

This should include :

  1. Enunciation of the problem, its history and probable causes, if any.
  2. Previous remedial measures taken, if any, their details and behaviour.56
  3. Details along with design and hydraulic calculations of existing/ proposed structures such as dam, weir, bridge, causeway, embankments, etc., which affect the river regime, in or near the problem reach of the river.
  4. Photographs depicting behaviour of the river during floods, and
  5. In case of erosion problems:
    1. The stage of the river at which the erosion is most pronounced; and
    2. Whether damage to bank occurs while gauge is rising or falling.

11.4.2. Survey data

  1. Index map: As indicated in para 4.1(i).
  2. River survey plan: As indicated in para 4.1 (ii), this plan should show:
    1. A close traverse covering the entire reach to be modelled
    2. Latitudes and longitudes
    3. Dry weather channel
    4. Formation of rapids, pools, etc.
    5. Position of existing and proposed structures like bridges, dams, weirs, barrages, ghats, spurs and other pucca structures, etc.
    6. Location of the problem area, and
    7. Various channels in case of a braided river.
  3. Aerial Survey plan: Same as indicated in para 4.5(v).
  4. Cross sections: In addition to data as indicated in para 4.1(iv), the cross-sections should cover the entire reach to be modelled (cross section interval would be specified in individual cases as this will depend on model scales). Positions of cross sections with their zero chainages should be indicated on survey plan referred to in para 11.4.2(2).
  5. Contour plan: Same as indicated in para 4.1 (iii). This should, however, cover the entire reach mentioned in para 11.4.2(2).57
  6. Previous river surveys super-imposed on a plan indicating changes in the river course, if any.

Note: All levels shall be connected to the G.T.S. Bench Mark.

11.4.3. Hydraulic data

  1. Daily gauge and discharge data at all existing stream gauging sites for one or more flood seasons. If such sites are absent, a minimum of three new stations should be located, one each at either end of the reach to be modelled and one in the middle and data collected and furnished for at least one flood season. The positions of all gauge stations should be shown on plan mentioned in para 11.4.2(2) and their co-ordinates given.
  2. River cross-section at discharge site, indicating nature of river bed (sandy, boulders or rocky) and sample discharge calculations.
  3. Flood data: Same as indicated in paras 4.2 (vi), 4.2 (vii) and 4.2 (viii).
  4. RLS of flood marks on structures and depth of spill flow and its course.
  5. Discharge distribution in various channels at important stages.
  6. Catchment characteristics: As indicated in para 4.2 (i) to (iv).

Note: All gauge and discharge sites should coincide with cross sections and should be marked on survey plan referred to in para 11.4.2(2).

11.4.4. Sediment data

  1. Bed material data: Samples may be taken at three sections one at either end and one in the centre of river reach under consideration. These samples may be analysed for determination of particle size distribution and mean diameter.
  2. Bore hole data: Same as indicated in para 4.3(ii).58
  3. Bank material data: Material of which both banks are made is to be collected on the same sections from which bed samples are collected and/or in the reach where active erosion if noticed as indicated in para 4.2(xiv). The sample may be analysed for determination of following properties.
    1. Particle size distribution and weighted mean diameter
    2. Field density
    3. Moisture content at field density
    4. Plasticity index and liquid limit
    5. Cohesion and angle of internal friction, and
    6. Angle of repose under water, if material is non-cohesive.
  4. Suspended sediment data: In addition to data as indicated in para 4.3 (iii), the following data is also required:

Suspended sediment data may be collected using suitable samplers near the central gauge station in the reach. Samples should be collected at medium and high flood stages. Samples may be analysed to estimate percentage of coarse, medium and fine fractions.

Note: Position of bed-bank material samples, bore-holes and sampling particles should be marked on survey plan referred to in para 11.4.2(2).

11.4.5. Other data

  1. Lines of flow at specific flood stages, low, medium and high.
  2. Design discharge, maximum flood discharge, waterway proposed, deepest scour and afflux.
  3. The drawing of piers, abutments, etc. and their foundation.
  4. Design and drawings of guide bunds.59

11.4.6. Terms of reference

  1. Terms of reference should be stated clearly by sponsoring authority.
  2. In case reach to be modelled includes tributaries or branches or confluence of two rivers, similar data would be required for each of the concerned reaches.

11.5. Model Limitations

11.5.1.

While some type of problems can be solved with the aid of model studies with a high degree of accuracy, certain aspects of studies connected with the rivers flowing in alluvium present difficulties. In the mobile bed river models, the results lack scalar transformation to the prototype. They cannot, therefore, be applied quantitatively but can be regarded as qualitative. Some of these aspects are described in Appendix-4. Suitable model techniques have been devised to reduce the gap between model results and natural occurrence showing what may be reasonably expected from the model results and what should not be expected. Models are always helpful in that, they make it easier to visualise the problems and evaluate the relative affects of different treatments making allowance for model limitations, but the success depends primarily on correct diagnosis and evaluation of all factors causing change.

11.5.2.

In the final analysis, the validity of results of model study and interpretation of its results depends on experience, sound judgement and reasoning of the experimenter.

12. INSPECTION

12.1. Purpose

The successful functioning of any river training and protective work depends to a great extent on its proper design, construction and maintenance. After completion of river training and protective works, a close watch must be kept on their performance so that timely action, wherever necessary, can be taken to avoid major damages and difficulties at a later date.60

12.2. Frequency and Scope

The protective works like guide bunds spurs, pitching around abutments, etc., shall be inspected.

  1. about a month before the flood season
  2. during the floods and
  3. immediately after the floods

The inspection before the floods shall be carried out to ensure that all flood protection measures have been carried out as per design in case of new works. In case of existing works it will be ensured that these are intact and in position as per design and drawings.

Inspection during the floods shall be carried out to have information about HFL obtained, scouring of bed, and launching of apron etc., so as to take corrective measures as soon as required. The inspecting officer must look for aspects like launching of the apron, settling of the slopes, piping action, improper drainage of the rain water causing the slope to be disturbed, impact of waves, carrying away of the smaller particles and thus disturbing the slope, any undue scour at the nose of the bund and/ or at the toe of the pitching and give his recommendations to ensure that the protective works function adequately. The quantity of reserve stones available at site for meeting emergent situations shall be checked before floods against specified quantity and duly reported.

The floor protection shall also be inspected before, during and after the floods to ascertain the extent of scour, cracking and damage of the floor, if any and adequacy of the cut off walls and apron, etc. Specific recommendations for augmentation of the existing provisions, if any, shall also be given.

12.3. Points to be Kept in View

  1. (Most careful patrolling and watch is necessary during each flood season especially the first flood season to detect any weakness in construction and to take corrective action promptly.61
  2. The Engineer-in-charge should acquaint himself with the past history of the protective works and the behaviour of the river as it is only when he possesses all this knowledge that he can deal effectively with any problem that may arise.
  3. It is advisable to have a reserve quantity of stone which can be used in case of an emergency. A part of the stone may be stacked on the guide bund itself and a part in the nearest store from where it can be loaded and transported quickly to site. The quantity of reserve boulders would depend upon site conditions. However, 2 per cent of the total quantity of boulders used in apron and slope pitching may be kept as reserve in stock for emergent use.
  4. It is necessary that during the flood season the field Engineers remain vigilant and keep a careful watch on the behaviour of the river as it affects the training works. During flood season it is advisable to have regular patrolling of the guide bund and the approach banks and proper action taken when any abnormal swirls, eddies or scour are apprehended. Any small rain cuts or displacement by waves along the guide bund or the approach bank must be repaired immediately as there is always the danger of a small cut developing into a major disaster, if not, attended to.
  5. Any settlement in the bank or bridge or slip in the slope needs immediate attention.
  6. During winter or dry weather a survey of the river course has to be carried out to a sufficient distance on the upstream and downstream of bridges with guide bunds.
  7. Soundings preferably with the help of an echo sounder shall be taken near the guide bund when the river is in flood.62

13. MAINTENANCE ASPECTS OF RIVER TRAINING AND PROTECTIVE WORKS

13.1.

Proper maintenance of river training and protective works is extremely important as damages to them can be more dangerous than damages to bridges where no protective works are provided. It is, therefore, important that maintenance Engineers are made aware of the design principles underlying the various provisions made in different protective works as well as likely causes and nature of damages so that their significance is very well understood and the maintenance is carried out effectively. They should also acquaint themselves with the past history of the bridges, their protective works and behaviour of the river as only when they possess all this knowledge that they can deal effectively with any maintenance problem.

Keeping the above in view the list of important records which should be available at site for proper maintenance has been drawn. But this list is by no means exhaustive and other records as necessary in each individual case should also be kept at site.

  1. Longitudinal section, cross section and plan indicating the course of the channel.
  2. Plan showing location of bridge.
  3. Salient design details of bridge and protective works.
  4. Plan indicating layout and dimensions of the embankment slope pitching, filter layers, cut off walls turfing launching apron, drains etc. and details of materials used in the construction grading, Liquid Limit, Plasticity Index Proctor Density and Optimum Moisture Content.
  5. Record of observed High Flood Level, discharge, velocity of flow, obliquity of flow, functioning of the bridge and protective works including changes in the flow-pattern. For important bridges gauge stations should be established to measure the discharge.
  6. Record of River Survey details upto a distance of 5 times the length of the bridge (or 1 km whichever is more) on upstream side and for a distance equal to 3 times the length of the bridge on downstream side alongwith cross sections at suitable intervals for the last ten years.
  7. Record by way of photographic evidence of the nature and extent of damages observed in the past and the remedial measures undertaken.63
  8. Copy of the model study report if model tests were got carried out for location of bridge and protective work.
  9. A record of satellite imagery for important bridges updated every five years through National Remote Sensing agency. In case any abnormal situation is observed then additional satellite imageries even at lesser intervals should be taken and record maintained.

13.2. The Maintenance Work can be Classified under two Categories:

  1. Pre-monsoon Maintenance Work
  2. Monsoon Maintenance Work
  1. Pre-Monsoon Maintenance Work
    1. Repairing or reconditioning the existing protective works to the original design section in advance so that these can withstand the pressure of the ensuing flood.
    2. Ensuring adequate free board to cater for any unexpected settlement with the aggradation of the river bed by wave action or occurrence of flood of higher intensity than the designed one, without any adverse effect on the performance of bridge and protective works.
    3. Filling up all hollows and depressions in the embankment of the guide bunds wherever existing and ramming earth after clearing the site of all loose and vegetal materials.
    4. Providing a cover of soil containing 10 per cent to 15 per cent of clay well rammed and rolled where the filled top material is sandy or silty.
    5. Rodents and other animals make holes, cavities and tunnels through and under the embankment of the guide bunds. These are sources of danger causing excessive seepage which may give rise to serious breeches during flood period. Such holes should be carefully located, examined and provided with inverted filter, filled with earth and rammed. Alternatively such holes can be filled with well rammed stiff clay.
    6. Planting of trees on the top of guide bunds should not be permitted because their roots tend to loosen the core of the guide bunds. Deep rooted bushy shrubs or64

      short grass or both growing on the slopes of embankments is good protection against erosion and wave wash. Generally, the slopes should be turfed with grass sods.

    7. Examining necessity of Protective measures by revetment/rip-rap, launching apron, floor protection, etc., and carrying out the same before onset of monsoon, for bridge foundations, approach embankments and guide bunds which are in imminent danger of erosion.
    8. Top of guide bund wherever those are designed to carry vehicular traffic should be kept in good condition so that they effectively serve the purpose of transport of materials and inspection both during the monsoon and premonsoon periods.
    9. All Departmental vehicles, boats and launches should be kept operational. All tools and plants including torch lights hurricane lamps and spades, etc., and fire fighting articles as well as materials for erecting temporary sheds at the work sites for workers should be arranged and stored in a suitable place.
    10. Advance collection of sand bags, stone boulders, about 2 per cent of total quantity used in apron GI wire for making wire crates, for use in the event of emergency.
    11. (To take soundings near the bridge and protective works particularly at locations where the river is showing a tendency to meander to compare actual observed sour near bridge foundations and protective works with designed scour.
    12. Proper communication system should be installed for quick transmission of messages to higher authorities.
  2. Monsoon Maintenance Work
    1. During Monsoon very careful maintenance of the Protective Works is required as the flood water of river threatens, safety of the guide bunds, spurs and approach embankments. It assumes further importance in case of new guide bunds. The establishment required to be engaged for proper maintenance will depend upon the importance and behaviour of the river. As soon as the water touches the guide bunds and shows further rising trend in its level, a control room should be set up and round the clock patrolling should start. This should continue until water recedes the Low Water Level. During this period inspection by senior official should also be carried out.65
    2. Special vigilance is necessary towards the country side of the guide bund to detect any formation of boils due to seepage which call for immediate attention.
    3. In the event of abnormal rise in water level threatening the washing away of the guide bund, the level of the top of the guide bund may be suitably raised. The common method of building up the height is by providing dowel on the river side of the top of the guide bunds with bags filled with earth. These bags should be half full only so that these will fit closely against each other. Sand should not be used for filling the sacks, if clay or loamy soil is available.
    4. During floods scour depth should be measured daily and in case it exceeds designed scour depth dumping of boulders in the scour hole should be resorted to with large size boulders as well as boulders in wire crates.
    5. In case of displacement of slope pitching/filter media the same should be immediately restored wherever necessary with sand bags/stone boulders/stone in wire crates/ cement concrete blocks.
    6. After the flood season when the water level has fallen, cross-sections should be taken at every 50 m interval along the length of the guide bund or spurs by probings wherever necessary to ascertain the position of the stone in the slope and the apron. The cross-sections will indicate the progress in launching of the apron, its ultimate position and reveal any defect that may require remedy. The cross-sections taken after each flood season should be compared with the original cross-sections, to examine the variations, if any. The damages to protection work should be restored to its original position by dumping further quantity of loose stone of required size or boulders in wire crates wherever necessary. Damaged wire crates should be replaced.
    7. Model tests and field observations have confirmed that for satisfactory launching of apron the bed materials should scour easily and evenly. If an apron is laid on the river bed consisting of alternate layers of sand and clay, the sand layers scour and clayey layers subside causing uneven cliffs as a result the apron cannot launch uniformly. Stones fall in the river bed and are washed away by the water current. Therefore, clayey beds cannot be used as dependable foundations for aprons. In places where clayey beds are unavoidable sufficient quantity of reserve stone at hand should be kept to fill the uneven depressions and scour holes as well as to repair the other damages.
    8. (The launching apron if damaged should be repaired by diverting the flow, if necessary. During such repairs the portion launched should not be disturbed and new crated sausage work should be provided over it.66
    9. In the case of major damages like slope failure or major changes in river behaviour it may be necessary to close the bridge to traffic pending restoration on immediate basis which should be based on re-assessment of the damages noticed, design parameters past and present.
    10. In the case of bridges and protective works which are in imminent danger every year, permanent remedial measures should be finalised only on the basis of model studies.67

FORMULA FOR COMPUTATION OF AFFLUX

Afflux is approximately calculated using Molesworth formula given below:

Appendix 1(a)
(Para 4.6.3)

Image

Where

*h1 = afflux in metre

V = average velocity of river prior to obstruction in metre sec.

A = unobstructed sectional area of river in sq. metre.

A1 = sectional area of river at obstruction in sq. metre.68

Appendix 1
(Sub-para 4.6.3)

METHOD FOR COMPUTATION OF BACKWATER OR AFFLUX AT BRIDGE PIERS FOR RIVERS CARRYING DISCHARGE MORE THAN 3000 m3/sec.

1. BACKWATER OR AFFLUX

The profile along the centre of the stream at the bridge site is given in Figs. 1 and 2. The rise in water level above normal water surface at Section 1 due to construction of the bridge is denoted by h*1 and is called the backwater of afflux.

Fig. 1. Normal crossing-wing wall and abutments

Fig. 1. Normal crossing-wing wall and abutments69

Fig. 2. Normal crossing-spill-through abutments

Fig. 2. Normal crossing-spill-through abutments70

2. EXPRESSION FOR COMPUTATION OF BACKWATER (AFFLUX)

A practical expression for backwater has been formulated by applying the principle of conservation of energy between the point of maximum backwater upstream from the bridge Section 1 and a point downstream from the bridge at which normal stage has been re-established in Section 4 (Figs. 1 A and 2 A). The expression is reasonably valid if the channel in the vicinity of the bridge is essentially straight, the cross sectional area of the stream is fairly uniform, the gradient of the bottom is aproximately constant between sections 1 and 4, the flow is free to contract and expand, there is no appreciable scour of the bed in the constriction and the flow is in the sub-critical range.

The expression for computation of backwater h*1 (in FPS units) upstream from a bridge constricting the flow, formulated on the basis of model studies is as follows:

Image

To compute backwater, it is necessary to obtain the approximate value of h*1 by using the first part of expression (1)

Image

The value of A1 in the second part of the expression (1) which depends on h*1 can then be determined and the second terms of expression (1) evaluated.

3. BACKWATER COEFFICIENT

3.1.

The value of the overall backwater coefficient K* is dependent on the following:

  1. The bridge opening ratio M, i.e., the degree of stream constriction involved, expressed as the ratio of the flow which can pass unimpeded through the bridge constriction to the total flow of the river and type of bridge abutments.
  2. Number, size, shape and orientation of piers in the constriction.
  3. Eccentricity or asymmetric position of bridge with respect to the valley crosssection; and
  4. Skew (bridge crosses stream at other than 90° angle).

3.2. Base coefficient (Kb):

Kb is the backwater coefficient for a bridge in which only

the bridge opening ratio M is considered. Knowing the type of abutments, shape of wing walls and the value of M, use Fig. 3 for estimating Kb.71

Fig. 3. Backwater coefficient base curves (sub-critical flow)

Fig. 3. Backwater coefficient base curves (sub-critical flow)

3.3. Effect of Piers (normal crossing)

The introduction of piers in a bridge causes constriction and consequential backwater. This incremental backwater coefficient is designated as Δ Kp, which can be obtained from Fig.4. By entering chart-A with the proper value of J and reading upwards to the proper pier type, Δ K is read from the ordinate. Obtain the correction factor, σ from Chart-B in Fig.4 for opening ratios (M) other than unity. The incremental backwater coefficient is then

Image

3.4. Effect of Piers (skewed crossings)

In the case of skewed crossings, the effect of piers is calculated as for normal crossings except for the computation of J, An2 and M. The pier area for a skewed crossings Ap is the sum of the individual pier areas normal to the general direction of flow as illustrated in Fig. 4. An2 for a skewed crossing is based on the projected length of the bridge bs cos ϕ and also includes the area occupied by the piers. The value of J is the pier area. Ap, divided by the projected gross area of the bridge constriction, both measured normal to72

Fig. 4. Incremental backwater coefficient for piers

Fig. 4. Incremental backwater coefficient for piers73

the general direction of flow. The computation of M for skewed crossing is also based on the projected length of bridge.

3.5. Effect of Eccentricity

The magnitude of the incremental backwater coefficient Δ Ke accounting for the effect of eccentricity can be calculated from Fig. 5. Eccentricity is defined as 1 minus the ratio of the lesser to the greater discharge outside the projected length of the bridge or

Fig. 5. Incremental backwater coefficient for eccentricity

Fig. 5. Incremental backwater coefficient for eccentricity74

Image

(if the cross section is extremely asymmetrical so that Qa < 20 per cent of Qc or vice versa, the afflux coefficient will be some what larger than for comparable value of M shown on the base curve).

3.6. Effect of Skew

The method of computation of incremental backwater coefficient ΔΚ5 for the skewed crossing differs from that of normal crossing in the following respects:

The bridge opening ratio M is computed on the projected length of bridge rather than on the length along the centre-line. The length is obtained by projecting the bridge opening upstream parallel to the general direction of flood flow as shown in Fig.6. The general direction of flow means the direction of flood flow as it existed previous to the placement of the embankments in the stream. The length of the constricted opening is bs cos ϕ and the area An2 is based on this length. The velocity head, V2n2/2g to be substituted in expression (1) is based on the projected area An2. Fig. 7 may be used for determining the incremental backwater coefficient (ΔΚ5) for the effect of skew, for wing walls and spill-through type abutments. It varies with opening ratio M, the angle of skew of the bridge ϕ, with the general direction of flood flow and the alignment of the abutment faces as indicated by the sketches in Fig. 7.

Image

4. KINETIC ENERGY COEFFICIENT

A weighted average value of the kinetic energy is obtained by multiplying the average velocity head computed as (Q/A1)2/ 2g by a kinetic energy coefficient α1 defined as

Image

A second coefficient α2 is required to correct the velocity head for non-uniform velocity distribution under the bridge.75

Fig. 6. Skewed crossings

Fig. 6. Skewed crossings

Image

The value of α1 can be computed but α2 is not readily available, knowing the value of 1 and opening ratio M, use Fig. 8 for estimating α2.76

Fig. 7. Incremental backwater coefficient for skew

Fig. 7. Incremental backwater coefficient for skew77

Fig. 8. Aid for estimating

Fig. 8. Aid for estimating 278

5. Having known the value of K*, α2 and Vn the approximate value of h*1 using the first part of the expression (1) is first determined. The value of A1 in the second part of the expression (1) which depends on h*1 can then be determined and the second term of expression (1) is evaluated and total backwater or afflux h*1 (in ft) found.

Note: The extract given in this Appendix has been taken from the Book “Hydraulics of Bridge Waterways” with the permission of U.S. Deptt. of Transportation (Federal Highway Administration).79

Appendix 1 (b)
(Contd.)

(Para 4.6.3)

NOTATIONS

Symbol Definition Reference to Fig.
A1 = Area of flow including backwater in section 1 (sq.ft.) 1(B) and 2(B)
An1 = Area of flow below normal water surface in section 1 (sq.ft.) 1(B) and 2(B)
A2 = Area of flow including backwater in section 2 (sq.ft.) 1(C) and 2(C)
An2 = Gross area of flow in constriction below normal water surface at section 2(sq.ft.) 1(C) and 2(C)
A4 = Area of flow at section 4 at which normal water surface is re-established (sq.ft.) 1(A) and 2(A)
Ap = Projected area of piers normal to flow, between normal water surface and stream bed) (sq.ft.) 4
b = Width of constriction (ft.) 1(C) and 2(C)
bs = Width of constriction of a skew crossing measured along centre line of roadway (ft.) 6
e = Image
g = Acceleration due to gravity = 32.2 ft./sec2
h1* = Total backwater (afflux) or rise above normal stage at section 1 (ft) 1(A) and 2(A)
J =

Image= Ratio due to area obstructed by piers to gross area of bridge waterway below normal water surface at section 2

4
Kb = Backwater coefficient from base curve 3
∆Kp = Incremental backwater coefficient for piers 480
ΔΚe = Incremental backwater coefficient for eccentricity 5

ΔΚs

= Incremental backwater coefficient for skew 7
K* = Kb+∆Kp+∆Ke+∆Ks
Total backwater coefficient for sub-critical flow
M = Bridge opening ratio Image

Image

Qb = Flow in portion of the channel within projected length of bridge at section 1 (cusecs) 1 and 2
QaQc = Flow over that portion of the natural flood plain obstructed by the roadway embankment (cusecs)1 and 2
Q = Qa + Qb + Qc = Total discharge (cusecs)
q = Discharge in sub-section (cusecs)
v2 = ImageAverage velocity at Section-1 (ft/sec.)
v2 ImageAverage velocity in constriction at section 2 (ft/sec.)
Vn2 = ImageAverage velocity in constriction for flow at normal stage (ft/sec.)
V = Average velocity in a sub-section (ft/sec)

1

= Velocity head coeffcient at Section 1
2 = Velocity head coefficient for constriction 8
σ = Multiplication factor for influence of M on incremental backwater coefficient for piers 4(B)
ϕ = Angle of skew (degrees) 681

Appendix 2
(Para 5.3.7.3)

1. DETAILS OF WIRE MESH CRATES

For laying of wire crates in aprons of bridges, two situations arise.

  1. Where the crates are to be laid in deep water and have to be dumped and then joined together.
  2. Where depth of water is low or dry bed is available. In such cases, the crates can be laid at site.

2. WIRE CRATES

Wire crates shall be made from hot dip galvanised mild steel wire of dia, not less than 4 mm in annealed condition having tensile strength of 300-450 MPa conforming to IS: 280-1978 (soft). The galvanised coating shall be heavy coating for soft condition conforming to IS: 4826 - 1979. The mesh of crate shall not be more than 150 mm. Wire crates for shallow accessible situations shall be 3m × 1.5 m × 1.25 m in size. Where these have to be deposited and there is a chance of overturning, the crate shall be divided into 1.5 m compartments by cross netting.

For deep or inaccessible situations, wire crates can be made smaller subject to approval of the Engineer-in-Charge.

Wire crates built in-situ, shall neither be larger than 7.5 m × 3.0 m × 0.6 m nor smaller than 2 m × 1 m × 0.3 m. Sides of large crates shall be securely stayed at intervals not exceeding 1.5 m to prevent bulging.

The netting shall be made by fixing a row of spikes on a beam at a spacing equal to the mesh. The beam must be a little longer than the width of netting required. The wire is to be cut to lengths about three times the length of the net required. Each piece is bent at the middle around one of the spikes and the weaving commenced from one comer.

A double twist shall be given at each inter-section. This twisting shall be carefully done by means of a strong iron bar, five and half turns being given to the bar at each splice.

The bottom and two ends of the crate or mattress shall be made at one time. The other two sides shall be made separately and shall be secured to the bottom and the ends by twisting adjacent wires together. The top shall be made separately and shall be fixed in the same manner as the sides alter the crate or mattress has been filled.

Wherever possible, crates shall be placed in position before filling with boulders. The crates shall be filled by carefully hand packing the boulders as tightly as possible and not by merely throwing in stones or boulders.82

Appendix 3
(Para 11.2.4)

MATHEMATICAL MODEL STUDIES

1. INTRODUCTION

1.1.

The alluvial rivers are regulatory in the sense that they adjust their characteristics in response to any change in the environment. These environmental changes may occur naturally or may be result of such human activities as river training, diversion, construction of dams, channelisation, bank protection, constriction of bridges, sand and gravel mining etc. Such changes distort the natural equilibrium of a river. The river will adjust to the new conditions by changing its slope, roughness, cross sectional shape or meandering pattern. Within the existing constraints, any one or combination of these characteristics may adjust as the river seeks to maintain the balance between its ability to transport the sediment and the sediment load imposed.

1.2.

River channel behaviour often needs to be studied in its natural state and its responses to the afore mentioned human activities. Studies of river hydraulics, sediment transport and river channel changes may be through physical modelling or mathematical modelling or both. Physical modelling has been relied upon traditionally to obtain the essential design information. What limits the accuracy of physical model is the scale distortion which is almost unavoidable particularly when it involves sedimentation. Mathematical modelling of erodible channels has been advanced with progress in physics of fluvial processes and computer techniques. Since the actual size river is applied in mathematical modelling, there is no scale distortion. The applicability and accuracy of model depends on the physical foundation and numerical techniques employed.

1.3.

Mathematical model of river channel changes require adequate and sufficient physical relationships for the fluvial processes. Although the processes are governed by the principles of continuity, flow resistance, sediment transport and bank stability, such relations are insufficient to explain the time and spatial variations of channel geometry in an alluvial river. Generally width adjustment occurs concurrently with changes in the river bed profile, slope, channel pattern, roughness and so on. These changes are closely inter related and delicately adjust to establish or to maintain the dynamic state of equilibrium. While any factor imposed upon the river is usually absorbed by the combination of the above responses, the extent of each type of resistances is inversely related to the resistance to change. For example, in response to deficit in sediment supply, the slope of the river is generally reduced more through meander development than through degradation because the latter is usually inhibited by the coarsening of the bed material. Also, there tends to be more adjustment in width in erodible bank materials than in erosion resistant bank materials.83

1.4.

The following are some of the cases where man made changes affect the dynamic equilibrium of the river:

  1. Storage Dam for Power Generation constructed upstream of a bridge - The effect of dam upstream is that the time distribution of flow is changed although the total volume is not. The flood peaks are reduced and the sediment transport is cut off. These conditions may induce excessive scour near the bridge.
  2. Construction of Dam Downstream of a bridge - Aggradation occurs as the river flow slows down upon entering the reservoir and deposits its sediment load. The method of deposition is usually complex in rivers with fine sediment load but in coarse sand bed rivers, the sediment is largely deposited at the entrance of the reservoir in a delta form.
  3. Strengthening of Upstream Embankments - There are several consequences when the minor channels are diverted under the main bridge by construction of upstream embankments. First, the bridge obstruction increases the depth of flow immediately upstream and so worsens the local flooding problem. The concentrated overbank flow returns to the river just upstream of the bridge to cause land erosion. The increased flow in the channel increases the channel scour and bank attack until the excess flow can return to the downstream flood plane.
  4. Backwater with Aggradation - Construction of a bridge on a constricted channel induces backwater effects. At the bridge crossing, because of a smaller width the stream bed continues to scour while on the upstream side because of a backwater effect deposition occurs. Channel widening in this reach would be expected.

2. MATHEMATICAL MODELLING

2.1. Water Routing

Water routing provides temporal and spatial variations of the stage, discharge, energy gradient and other hydraulic parameters in the channel. The water routing component has the following major features:

  1. Numerical solution of the continuity and momentum equations for longitudinal flow,
  2. Evaluation of flow resistance due to longitudinal and transverse flows, and
  3. Upstream and downstream boundary conditions.

The continuity and momentum equations in the longitudinal direction are derived as follows:

Image84

Image

Where Q = discharge
A = cross sectional area of flow
t = time
X = longitudinal direction along the discharge centre line measured from the upstream entrance
q = lateral inflow rate per unit length
H = stage of water surface elevation
S = energy gradient
g = acceleration due to gravity

The upstream boundary condition for water routing is the inflow hydrograph and the downstream condition is the stage discharge relation.

The longitudinal energy gradient can be evaluated using any valid flow resistance relationship. If Manning’s formula is employed, the roughness coefficient ‘n’ must be selected according to the bed diameter and river conditions.

2.2. Sediment Routing

The sediment routing component has following major features:

  1. Computation of sediment transport capacity using a suitable formula for the physical conditions
  2. Determination of actual sediment discharge by making corrections for availability, sorting and diffusion
  3. Upstream conditions for sediment inflow
  4. Numerical solution of the continuity equation for sediment

These features are evaluated at each time step and results so obtained are used in determining the changes in channel configuration. To treat at the time dependent and non equilibrium sediment transport the bed material at each section is divided into several size fractions and sediment transport is computed using suitable formula.

The equation of continuity for sediment in the longitudinal direction is given by:

Image

Where λ = porosity of the bed material
Qs = bed material discharge
qs = lateral inflow rate of sediment per unit length85

According to this equation, the time change of cross sectional area is related to the longitudinal gradient in sediment discharge and lateral sediment inflow. In the absence of lateral sediment inflow, longitudinal imbalance in Qs is absorbed by channel adjustments towards establishing uniformity in Qs.

The change in cross sectional area for each section at each time step is obtained through numerical solution of Equation 3. This area change will be applied to the bed and banks following correction techniques for channel width and channel bed profile.

2.3.

One dimensional mathematical models like water routing and backwater models to solve problems such as dam break, flood wave transmission, effect of bridge constriction etc. were commonly in use before the introduction of computers. Now with the easy access to mainframe computer and personal computers with large memories, it has become possible to develop software and study the morphological changes of short and long duration by simulation models. Institutes such as Central Water Commission, Central Water and Power Research Station, Pune, National Institute of Hydrology, Roorkee, and some of the State Irrigation Research Institutes and Indian Institute of Technology at Delhi, Bombay etc. have developed suitable softwares to study these aspects in the area of river engineering.86

Appendix 4
(Para 11.5.1)

MODEL LIMITATIONS

1.

In the mobile bed river model, the results lack scalar transformation to prototype. They cannot be applied quantitatively, however, they can be considered as qualitative. Some of these are:

1.1. Exaggerated Scour Holes

Silting in model is much slower than in the prototype while the scouring takes place during the early stages of the hydrograph in model. Firstly, this suggested scour hole is due to dissimilar horizontal and vertical scales, scour holes tend to be proportional to vertical scale while the width tends to be proportional to horizontal scale. Secondly, in falling stages of the hydrograph bed movement in model is negligible, as such the scour hole which used to be filled up in prototype does not fill up in model. However, the scour depth obtained gives an idea of the formation and direction of new channels and is helpful for design of launching apron.

1.2. Non-reproduction of Silting in Model

In prototype, most of the sediment moves in suspension and very little as bed load. Silting is mostly due to suspended sediment, while in model, bed load is much higher than the suspended. Moreover, due to limited length and duration of run of model the suspended sediment does not settle down. The silting is only indicated by the slack flow or return flow of low intensities.

1.3. Incorrect Throw Off

Throw off in distorted model is different from the corresponding throw off in the prototype. This is partly due to the increased height in comparison to width of the structure, and partly due to very steep side slopes. Some of the research institutes have constructed full width as well as part width river models to reproduce approximately similar effects. First full width river model is constructed to small scales, the entry conditions in part width model are adjusted to reproduce the lines of flow observed from full width model. The throw off in part width model obtained is reproduced in full width model. The process is repeated till approximate similarity is obtained.

1.4. Incorrect Meandering

Due to uncertainty of uniform bed movement, further development of meanders in case of meandering rivers, is not correctly reproduced in the distorted models, It is due to this reason that correct development of new channels, resurvival of old channels and further silting of islands is seldom depicted from these models.87

1.5. Longitudinal Distortion

In vertically exaggerated models for bridges and barrages the thickness of the piers is much less and the width to depth ratio of model span and prototype span is not same. As such sometimes either number of piers are reduced to maintain the above ratio, or a few piers are combined to form one pier, the shape of such piers differs from that in prototype and effects the coefficient due to changed shape.

1.6. Different Time Scale

To reproduce correct silting in model, the hydrograph in the model should be run for a longer time. This time is defined as hydraulic time and the time scale for hydraulic time is:

(T1)r = Lr hr(-05)

When the sediment movement is guided by tractive force and the sedimenting time scale could be obtained by tractive force method, this works out to (T2)r = hr1.5. The only solution to this is that hr should be equal to Lr0.5 which results in higher exaggerations so more departure from prototype. Generally, time scale adopted is hydraulic time. In the above formulae (T1)r and (T2)r are the time scales, Lr is the length scale and hr is the height scale of the model.88

REFERENCES

  1. Manual on River Behaviour, Control and Training; Central Board of Irrigation and Power, Publication No.60 (Revised) 1971.
  2. INGLIS, C.C., “The Behaviour and Control of Rivers and Canals”, Research Publication No.13, Central Water Irrigation and Navigation Research Station, Pune.
  3. SPRING, F.J.E., “River Training and Control on the Guide Bank System”, Government of India, Technical Paper No. 153, 1903.
  4. “Scour at Bridge Piers,” Central Board of Irrigation and Power, Status Report No. 4, September, 1974.
  5. “River Training and Bank Protection,” Flood Control Series No. 4, United Nation Economic Commission for Asia and the Far East, Bangkok, 1953, pp. 16-17.
  6. SETHI, H.K.L. (1960), “River Training and Control for Bridges”, Technical Paper No.335, Research Designs and Standards Organisation, Ministry of Railways, Lucknow.
  7. BARDLEY, J.N., “Hydraulics of Bridge Waterways”, Hydraulic Design Series No.l, U.S. Deptt. of Transportation/Federal Highway Administration, (2nd edition revised March, 1978).
  8. Ministry of Shipping and Transport (Roads Wing)’s Specification for Road and Bridge Works (Published in 1978).
  9. GALES, R., “The Principles of River Training for Railway Bridges and their Application to the case of Harding Bridge over the Lower Ganga at Sora,” Journal of the Institution of Engineers, December, 1938.
  10. 1SHARMA, H.D. and ASTHANA, B.N., “Study of Waterway for Bridges and Barrages,” Irrigation and Power Journal, Vol.33, No.3, July, 1976, New Delhi.
  11. GARG, S.P., ASTHANA, B.N. and IAIN, S.K., “River Training of Bridges and Barrages.” Journal of Institution of Engineers (India), Vol.5, May, 1971.
  12. BALWANT RAO, B., NARAIN, A.D., and MOTWANI, S.C., “Protection to Approach Embankments of Highway Bridges,” Indian Highways, December, 1975.
  13. GARG, S.P., ASTHANA, B.N. and JAIN, S.K., “Design of Guide Bunds for Alluvial Rivers.” Journal of Institution of Engineers (India), Vol. 52, Sept., 1971.89
  14. Indian Standard No. IS: 8408, 1994, “Planning and Design of Groyens in Alluvial River Guidelines,’’ (First Revision).
  15. Standard Specifications and Code of Practice for Road Bridges, Section I, (IRC: 5-1985).
  16. Standard Specifications and Code of Practice for Road Bridges, Section-VII, Foundations and Substructure (IRC: 78 - 1983).
  17. Manual for Highway Bridge Maintenance Inspection - IRC Special Publication 18.
  18. Indian Standard No. IS: 10751, 1994, Planning and Design of Guide Banks for Alluvial Rivers, Guidelines (First Revision).90