This library of books, audio, video, and other materials from and about India is curated and maintained by Public Resource. The purpose of this library is to assist the students and the lifelong learners of India in their pursuit of an education so that they may better their status and their opportunities and to secure for themselves and for others justice, social, economic and political.

This item has been posted for non-commercial purposes and facilitates fair dealing usage of academic and research materials for private use including research, for criticism and review of the work or of other works and reproduction by teachers and students in the course of instruction. Many of these materials are either unavailable or inaccessible in libraries in India, especially in some of the poorer states and this collection seeks to fill a major gap that exists in access to knowledge.

For other collections we curate and more information, please visit the Bharat Ek Khoj page. Jai Gyan!

END OF PREAMBLE (NOT PART OF THE STANDARD)

IRC:SP:16-2004

GUIDELINES FOR SURFACE EVENNESS OF HIGHWAY PAVEMENTS

(First Revision)

Published by

THE INDIAN ROADS CONGRESS
Jamnagar House, Shahjahan Road,
New Delhi-110011
2004

Price Rs. 100/-
(plus packing and postage)

PERSONNEL OF THE HIGHWAYS SPECIFICATIONS AND STANDARDS COMMITTEE

(As on 20.12.2003)

1. The Addl. Director General (Road)*
(Convenor)
Ministry of Road Transport & Highways, Transport Bhavan, New Delhi -110001
2. G. Sharan
(Co-Convenor)
Chief Engineer (R&B) S&R, Ministry of Road Transport & Highways, Transport Bhavan, New Delhi-110001
3. The Chief Engineer (R&B) S&R
(Member-Secretary)
(G. Sharan) Ministry of Road Transport & Highways, Transport Bhavan, New Delhi-110001
Members
4. A.P. Bahadur Chief Engineer, Ministry of Road Transport & Highways, Transport Bhavan, New Delhi-110001
5. P.K. Chakrabarty Chief General Manager (NS), National Highv/ays Authority of India, Plot G:5-6, Sector 10, Dwarka New Delhi-110045
6. P.K. Datta Executive Director, Consulting Engg. Services (I) Pvt. Ltd., 57, Nehru Place, New Delhi-110019
7. J.P. Desai Sr. Vice President (Tech. Ser.), Gujarat Ambuja Cements Ltd., Ambuja House, Ishwarbhuwan Road, Navrangpura, Ahmedabad-380009
8. Dr. S.L. Dhingra Professor, Transportation System, Civil Engg. Department, Indian Institute of Technology, Mumbai Powai, Mumbai-400076
9. D.P. Gupta DG(RD) (Retd.), E-44, Greater Kailash (Part I) Enclave, New Delhi-110048
10. S.K. Gupta Chief Engineer PWD, Almora
11. R.K. Jain Chief Engiener (Retd.), House No. 452, Sector 14, Sonepat-131001
12. Dr. S.S. Jain Professor & Coordinator (COTE), Deptt. of Civil Engg., Indian Institute of Technology, Roorkee, Roorkee-247667i
*ADG(R) being not in position. The meeting was presided by Shri G. Sharan (Co-Convenor), Chief Engineer (R&B) S&R, MORT&H
13. Dr. L.R. Kadiyali Chief Executive, L.R. Kadiyali & Associates, X-15 (First Floor), Hauz Khas, New Delhi-110016
14. Prabha Kant Katare Joint Director (PI), National Rural Road Dev. Agency (Min. of Rural Dev.), NBCC Tower, 5th Floor, Bhikaji Cama Place, New Delhi-110066
15. J.B. Mathur Chief Engineer (Retd.), H.No.77, 1st Floor, Sector 15A, Distt. Gautam Budh Nagar, Noida-201301
16. H.L. Mina Chief Engineer-cum-Addl. Secy. to the Govt. of Rajasthan, P.W.D., Jacob Road, Jaipur-302006
17. S.S. Momin Secretary (Works), Maharashtra P.W.D., Mantralaya, Mumbai-400032
18. A.B. Pawar Secretary (Works) (Retd.), C-58, Abhimanshree Housing Society, Off Pashan Road, Pune-411008
19. Dr. Gopal Ranjan Director, College of Engg., Roorkee, Post Box No. 27, K.M. Roorkee-Hardwar Road, Vardhman Puram, Roorkee-247667
20. S.S. Rathore Secretary to the Govt. of Gujarat, R&B Department, Block No. 14/1, Sardar Bhavan, Sachivalaya, Gandhinagar-3 82010
21. Arghya Pradip Saha Sr. Consultant, M-504, Habitat (Highway) CGHS, B-19, Vasundhra Enclave, Delhi
22. S.C. Sharma DG(RD) & AS, MORT&H (Retd.), 175, Vigyapan Lok, 15, Mayur Vihar Phase-I Extn. (Near Samachar Apartments), Delhi-110091
23. Prof. P.K. Sikdar Director, Central Road Research Institute, P.O. CRRI, Delhi-Mathura Road, New Delhi-110020
24. Dr. C.K. Singh Engineer-in-Chief-cum-Addl. Comm-cum-Spl. Secy.(Retd.), House No. M-10 (D.S.) Hermu Housing Colony, Main Hermu Road, Ranchi (Jharkhand)
25. Nirmal Jit Singh Member (Tech.), National Highways Authority of India, Plot No. G:5-6, Sector 10, Dwarka, New Delhi-110045
26. A.V. Sinha Chief General Manager, National Highways Authority of India, Plot No. G:5-6, Sector 10 Dwarka, New Delhi-110045ii
27. N.K. Sinha DG(RD) & SS, MORT&H (Retd.), G-1365, Ground Floor, Chittranjan Park, New Delhi-110019
28. V.K. Sinha Chief Engineer, Ministry of Road Transport & Highways, Transport Bhavan, New Delhi-110001
29. K.K. Sarin DG(RD) & AS, MOST (Retd.), S-108, Panchshila Park, New Delhi-110017
30. T.P. Velayudhan Addl. D.G.B.R., Directorate General Border Roads, Seema Sadak Bhavan, Ring Road, Delhi Cantt., New Delhi-110010
31. Maj. V.C. Verma Executive Director-Marketing, Oriental Structural Engrs. Pvt. Ltd., 21, Commercial Complex, Malcha Marg, Diplomatic Encl., New Delhi-110021
32. The Chief Engineer
(NH)
(B. Prabhakar Rao), R&B Department, Errum Manzil, Hyderabad-500082
33. The Chief Engineer
(Plg.)
(S.B. Basu), Ministry of Road Transport & Highways, Transport Bhavan, New Delhi-110001
34. The Chief Engineer
(Mech.)
(V.K. Sachdev), Ministry of Road Transport & Highways, Transport Bhavan, New Delhi-110001
35. The Chief Engineer
(Mech.)
PWD, G Block, 4th Floor, Writers’ Building, Kolkata-700001
36. The Chief Engineer
(NH)
(Ratnakar Dash), Sachivalaya Marg, Unit IV, Bhubaneswar-751001 Distt. Khurdha (Orissa)
37. The Engineer-in-Chief (Tribhuwan Ram), U.P. P.W.D., 96, M.G. Road, Lucknow-226001
38. The Chief Engineer National Highways, PWD Annexe, K.R. Circle, Bangalore-560001
Ex-Officio Members
39. President
Indian Roads Congress
(R.R. Sheoran), Engineer-in-Chief, Haryana PWD, B&R, Chandigarh
40. The Director General
(Road Development) & Special Secretary
Ministry of Road Transport & Highways, Transport Bhavan, New Delhi-110001iii
41. Secretary,
Indian Roads Congress
(R.S. Sharma), Indian Roads Congress, Jamnagar House, New Delhi-110011
Corresponding Members
1. M.K. Agarwal Engineer-in-Chief, Haryana PWD (Retd.), House No.40, Sector 16, Panchkula-134113
2. Dr. C.E.G. Justo Emeritus Fellow, 334, 25th Cross, 14th Main, Banashankari 2nd Stage, Bangalore-560070
3. M.D. Khattar Executive Director, Hindustan Construction Co.Ltd., Hincon House, Lal Bahadur Shastri Marg, Vikhroli (W), Mumbai-400083
4. Sunny C. Madathil Director (Project), Bhagheeratha Engg. Ltd., 132, Panampily Avenue, Cochin-682036
5. N.V. Merani Principal Secretary, Maharashtra PWD (Retd.), A-47/1344, Adarsh Nagar, Worli, Mumbai-400025

1. INTRODUCTION

Surface evenness of highway pavements refers to the regularity of surface finish both in longitudinal and transverse directions. Almost in all major highway works executed, control of surface evenness has been introduced as a mandatory requirement. The existing standards and tolerances of surface evenness are prescribed in IRC Special Publication 16-1977 which was based on the Report of the IRC Subcommittee on Surface Characteristics of Pavements. The Subcommittee was constituted by the Specifications and Standards Committee in November, 1968 under the Convenorship of Shri Mahabir Prasad. The Subcommittee presented its Report in 1975 and was endorsed by the Specifications and Standards Committee in its meeting held on 5th January, 1976. Later the Report was approved by the Executive Committee and the Council at their meetings held on 14th April, 1976 and 27th August, 1976 respectively which was printed as IRC:SP: 16-1977.

The Flexible Pavement Committee (H-4) in its meeting held on 23rd September, 2000 (personnel given below) decided to revise the above mentioned document because of improvements observed in the surface evenness and roughness values of the wearing surface of highway pavements due to introduction of high level of sophistication and mechanization in road construction. The Committee assigned the work of preparing the draft document to Shri R.S. Shukla who gathered the evenness and roughness data from various projects and prepared the draft. The draft was discussed by the Flexible Pavement Committee in their meetings held on 10th February, 2001, 1st September, 2001, 17th May, 2002 and 16th November, 2002 and necessary modifications were incorporated.1

Personnel of Flexible Pavement Committee (H-4) from 2000 to 2002

S.C. Sharma .... Convenor
Secretary, R&B, Gujarat
(S.S. Rathore)
.... Co-Convenor
Dr. S.S. Jain .... Member-Secretary
Members
D. Basu Prof. C.G. Swaminathan
Dr. A.K. Bhatnagar C.E. (R) S&R & T&T, MORT&H
S.K. Bhatnagar (Jai Prakash)
Dr. Animesh Das Rep. of DG(W), E-in-C Br., AHQ
Dr. M.P Dhir (Col. R.N. Malhotra)
D.P. Gupta Rep. of DGBR
Dr. L.R. Kadiyali (J.P. Arora)
Dr. C.E.G. Justo Head, FPDn., CRRI
H.L. Mina (Dr. Sunil Bose)
Prof. B.B. Pandey Director, HRS, Chennai
R.K. Pandey (S. Saravanavel)
Ex-Officio Members
President, IRC
(S.S. Rathore)
DG (RD) & SS
(N.K. Sinha)
Secretary, IRC
(G. Sharan)
Corresponding Members
Sukomal Chakrabarti S.K. Nirmal
Dr. P.K. Jain Smt. A.P. Joshi
R.S. Shukla

The newly constituted Flexible Pavement Committee (personnel given below) considered the modified draft in its meeting held on the 1st August, 2003 and authorized the Subgroup comprising Shri S.C. Sharma, Dr. L.R. Kadiyali and Shri R.S. Shukla to finalise the draft for sending to Highways Specifications and Standards (HSS) Committee. The draft was finalized by the Subgroup in its meeting held on the 17th October, 2003.2

Personnel of Flexible Pavement Committee (H-4) from 2003 to 2005

S.C. Sharma .... Convenor
Chief Engineer (Roads),
PWD, Guwahati
(K. Hazarika)
.... Co-Convenor
Dr. S.S. Jain .... Member-Secretary
Members
Arun Bajaj Chief Engineer (R&B) S&R,
Sukomal Chakrabarti MORT&H
Dr. Animesh Das A Rep. of I.O.C., Faridabad
D.P. Gupta (B.R. Tyagi)
Dr. L.R. Kadiyali A Rep. of E-in-C’s Branch,
D. Mukhopadhyay AHQ, (Col. V.K.P. Singh)
Prof. B.B. Pandey Rep. of DGBR
R.K. Pandey (K.K.Y. Mahindrakar)
R.S. Shukla Area Coordinator (FP Dn.), CRRI
K.K. Singal (Dr. Sunil Bose)
Dr. A. Veeraragavan Director, HRS, Chennai
Ex-Officio Members
President, IRC DG (RD) & SS,
MORT&H
Secretary, IRC
Corresponding Members
Dr. P.K. Jain S.K. Nirmal
Dr. C.E.G. Justo The Manager (Bitumen), HPC,
J.T. Nashikkar Mumbai

The draft was discussed by HSS Committee in its meeting held on 20th December, 2003 and finalised with some modifications to be incorporated. The Executive Committee of the IRC in its meeting held on 21th December, 2003 approved the modified document for placing before the Council. The document was finally approved by the Council in its 170th meeting held on the 8th January, 2004 for printing with editorial corrections. This document3

presents the First Revision of IRC:SP:16-2004 “Guidelines for Surface Evenness of Highway Pavements”.

2. IMPORTANCE OF SURFACE EVENNESS

2.1.

Surface evenness affects vehicle speed, comfort, vehicle operating cost and safety and hence needs to be given careful consideration during initial construction and subsequent maintenance.

2.2.

The standard recommended for surface evenness enables the engineer to exercise control over the quality of construction.

2.3.

Standards have also been prepared for the road roughness of different types of surfaces to enable an evaluation of the condition of the surface and prioritize and establish further maintenance intervention levels.

3. MEASUREMENT OF SURFACE EVENNESS AND ROUGHNESS

3.1. Measurement of Surface Evenness

3.1.1. Metre straight edge :

The measurement and checking of surface evenness can be done by a 3-metre straight edge during construction soon after the completion of a short stretch. In case of layers involving bituminous pavements or cement concrete pavements extra care is needed to rectify the defects before the material cools down/sets.

The 3-metre straight edge is made of steel or box type aluminum alloy bar, with sectional dimensions of 75 mm x 125 mm. The edge should be perfectly straight and free from rust or other defects.

Depressions under the straight edge are measured with a graduated wedge. The wedge shall be metallic. The dimensions are: 600 mm long base, 30 mm thickness and 30 mm height at one end4

tapering to 1 mm at the other. Graduations are provided at the hypotenuse and on the sides in mm, relative to the height from the base. These graduations are meant to read undulations upto 25 mm with a least count of a minimum of 3 mm. The wedge is provided with a handle of suitable length for facilitating measurements in standing position.

For recording undulations in the longitudinal profile, the straight edge is put longitudinally in the middle of each traffic lane along a line parallel to the centre line of the road. For a single lane road measurement of unevenness is made on both sides of the center line.

The straight edge is placed at the starting point, wedge inserted between it and the test surface where the gap is maximum and recorded. The straight edge is then slided forward for about half of its length, i.e., 1.5 metre and wedge reading repeated. The straight edge need not always be moved forward but may be moved backward and forward to record the maximum undulations existing at a location. The undulations in excess of the permissible magnitude shall be marked with paint to be rectified immediately.

3.2. Measurement of Surface Roughness

The roughness of pavement surface is commonly designated as Unevenness Index Value and is expressed in surface roughness is measured by a bump integrator.

3.2.1. Bump integrator :

Either towed fifth wheel bump integrator or car-mounted bump integrator can be used for measuring the road roughness. These are response type road roughness measuring systems and are extensively used in the country for measurement of roughness.

Towed Fifth Wheel Bump Integrator

The indigenous version of this device is the Automatic Road Unevenness Research (ARUR). The equipment consists of a trailer5

towed by a vehicle. A standard pneumatic tyre wheel inflated to a tyre pressure of 2.1 kg/sqcm is mounted within the trailer chassis, with a single leaf spring on either side of the wheel supporting the chassis.’Two dashpots provide viscous damping between chassis and axle. The frame is provided with a counter weight at the front to make the device practically free from the effects of the vertical motion of the vehicle. A mechanical integrator makes cumulative measurements of the unidirectional vertical movement of the wheel relative to the chassis. The distance travelled is measured by a distance measuring unit. The test is conducted at a speed of 32 ± 1 km/hour. Unevenness/roughness Index is defined as the ratio of the cumulative vertical displacement to the distance travelled and is expressed in mm/km.

The equipment is driven over the road surface at a speed of 32 ± 1 km/hour, keeping steady motion and avoiding swerving. The observer will activate the main switch fitted on the panel board at the beginning of the section and switch it off at the end of the section. The readings of the revolution counter and integrating counters are noted and entered in the data sheet.

The bump integrator values are recorded when the wheel revolution counter records 460 units which correspond to 1 km. The brief description of the road surface is also noted as the observer travels over the surface. The fifth wheel should preferably travel on wheel path. For measurement of roughness, one measurement in each lane is recommended for riding comforts evaluation.

Car-Mounted Bump Integrator

The car-mounted integrator consists of an integrating unit as provided in the fifth wheel Bump Integrator. The integrating unit is fitted with the rear axle and mounted in the rear portion of the car or rear floor of a jeep.6

There are two sets of counters, one each for measurement of bumps and distance along with a switch on the panel board. Only one set of counter is used at a time. The advantage of having two counters is that one may be kept in use while the other is kept stand-by and will display the data of the previous run. In addition, the switching of the counters with the help of toggle switch provided in the panel board gives data exactly kilometre-wise. The power is drawn from the car itself.

The differential movement between the rear axle and the body of the vehicle due to road unevenness is measured by the upward vertical motion of a wire which is transmitted into unidirectional rotatory movement of the pulley of the integrator unit. There is an arrangement in the integrating unit for converting the rotational movement into electric pulses which is recorded by the counters. One count in electro-magnetic counter corresponds to 25.4 mm relative movement between axle and floor of the vehicle. One count in distance counter corresponds to 20 m length of distance travelled.

The road roughness is affected by the vehicle speed. A bump gets magnified if the vehicle speed is not maintained. Vehicle load is another factor which influences the roughness measurement. For getting the realistic values the vehicle speed must be maintained at 32 ± 1 kmph. The laden weight of the vehicle is also standardized. While taking measurements the vehicle should carry maximum three passengers. It should be ensured that the outer vehicle wheel travels on the wheel path.

3.2.2. Calibration of bump integrator :

Roughness of a pavement is indicative of its riding quality and level-of-service. The roughness values provide an important impact in taking decision for surface improvement and maintenance measures. It is, therefore, necessary that the measurements are accurate and reliable. However, in response type devices, significant variations are often encountered7

in roughness measurement. Physical changes in the instrument, like, wearing of the tyre, braking or replacement of leaf spring, replacement of clamping unit, towing hitch, etc. may lead to large variations in the machine output.

Thus, in order to ensure repeatability and reproducibility of measurement by the same machine and consistency in measurement from different machines, it is essential that the response of the device to the road surface roughness should be correct. Initial standardisation and subsequent recalibration of response type devices are essential. The new measurements obtained from the response type devices must be correct to the standard roughness scale by calibration. Procedures for Calibration equipment commonly employed are:

A brief description of the above calibration equipments including procedure for their use is given in Annexures 1, 2 and 3 respectively.

A number of test sites, 8 to 10, of straight sections of length 400 to 500 m, of different roughness level covering a wide range of spectrum of surface roughness ranging from very smooth to very rough are selected. Care is taken to ensure that sufficient approach length on either side is available to attain vehicle test speed before entering the starting point of the test section. The entire length of all selected sites should have uniform riding quality and free of surface defects. For better visibility, wheel paths are marked with a road marking paint. Both the starting and the ending point of each site are also marked clearly so that the operator can identify the starting and ending point of the section during data recording. Section roughness8

and the corresponding reference values for each section are recorded through any of the above mentioned calibration devices for developing the calibration. At each test site a number of runs are made till at least three sets of consistent data are obtained. Average of the three values is taken as the representative roughness value of the section.

The device to be calibrated also run on the identified sections and the roughness is measured. Based on these two sets of observations a correlation between the reference roughness and roughness measured by the bump integrator is established. From these relations the corrected roughness values are obtained.

4. RECOMMENDED STANDARDS FOR SURFACE EVENNESS OF HIGHWAY PAVEMENTS

4.1.

The recommended maximum permissible unevenness values for different types of surfaces are given in Table 1. These values are to be used in conjunction with the maximum permissible frequency values given in Table 2.

Table 1. Maximum Permissible Surface Unevenness for Road Pavements
Type of surfacing Maximum Permissible Surface Unevenness
Longitudinal profile 3-m straight edge (mm) Transverse profile camber template (mm)
1. Surface Dressing 10 8
2. Open Graded Premix Carpet* 8 6
3. Mix Seal Surfacing 8 6
4. Semi-Dense Bituminous Concrete 6 4
5. Bituminous Concrete 5 4
6. Cement Concrete 5 4
* These values are for mechanized construction. For manual construction, the tolerances may be increased by 2 mm9
Table 2. Maximum Permissible Frequency of Surface Unevenness in 300 M Length In Longitudinal Profile
S. No. Type of Surface Unevenness (mm) Maximum number of Surface Unevenness
NH/SH MDR and other lower category of roads
1. Surface Dressing 8 - 10 20 40
2. Open Graded Premix Carpet 6 - 8 20 40
3. Mix Seal Surfacing 6 - 8 20 40
4. Semi-Dense Bituminous Concrete 4 - 6 20 40
5. Bituminous Concrete 3 - 5 15 30
6. Cement Concrete 4 - 5 15 30

4.1.1.

The longitudinal profile shall be checked with a 3-metre straight edge at the middle of each traffic lane along a line parallel to the central line of the road. The maximum permissible number of surface unevenness in longitudinal profile in 300 m length shall be as given in Table 2.

5. RECOMMENDED STANDARD FOR ROUGHNESS VALUES

5.1.

The maximum permissible values of surface roughness measured with a bump integrator for different surfaces are given in Table 3.

5.2.

Newly constructed surfaces are expected to give roughness values corresponding to ‘Good’ category while the values under ‘Average’ and ‘Poor’ category indicate level-of-service and intervention level for maintenance. Surfaces with very low roughness values loose skid resistance and are not desirable from safety considerations. Such surfacings should receive prompt attention for restoring frictional resistance.10

Table 3. Maximum Permissible Values of roughness (mm/km) for Road Surface
S. No. Type of Surface Condition of Road Surface
Good Average Poor
1. Surface Dressing <3500 3500 - 4500 >4500
2. Open Graded Premix Carpet <3000 3000 - 4000 >4000
3. Mix Seal Surfacing <3000 3000 - 4000 >4000
4. Semi-Dense Bituminous Concrete <2500 2500-3500 >3500
5. Bituminous Concrete <2000 2000 - 3000 >3000
6. Cement Concrete <2200 2200 - 3000 >3000

6. QUALITY CONTROL

6.1.

Strict quality control measures shall be exercised for the achievements of the recommended values of surface finish both in terms of unevenness and ‘Good’ category roughness as measured by a Straight Edge and Bump Integrator respectively.11

Annexure-1

DIPSTICK FOR CALIBRATION OF BUMP INTEGRATOR

1. INTRODUCTION

This specification covers the details of use of dipstick for the calibration of Bump Integrator.

2. EQUIPMENT

Dipstick is a fully integrated data collection and processing system that measures and records road profiles accurately and quickly. The equipment consists of the following:

Sequential elevation differences are recorded automatically by the on - board computer. Recorded information is then transferred to a PC or compatible computer for analysis.

Software is included to calculate and print various profile statistics including the International Roughness Index (IRI), as well as the individual point elevation and local surface curvatures. A continuous scaled plot of surface profile can also be produced with a printer that has IBM Graphics. For correlation with 5th Wheel Bump Integrator Values, the following relation may be used:

BI = 630 (IRI)1.12
Where, BI = Bump Integrator Roughness in mm/km
IRI = International Roughness Index12

3. PROCEDURE

The Dipstick Profiler stands on two support legs. The operator simply "walks'' the Dipstick along a survey line alternately pivoting the instrument about each leg. In less than an hour, one technician can measure, record and analyze upto 600 equally spaced, colinear elevation points to an accuracy of ±0.15 mm per reading. Dipstick surveys take less than half the time and are more accurate than both optic and laser surveys. Data analysis is fully computerized.

Two digital displays show the elevation difference between the Dipstick two support legs. Each elevation difference reading is measured and automatically recorded.

Audible and visual signals alert the operator when each measurement is complete. An optional manual trigger is also available to allow the operator to initiate the recording of each reading.13

Annexure-2

‘MERLIN’ FOR CALIBRATION OF BUMP INTEGRATOR

1. SCOPE

This specification covers the method for use of MERLIN (Machine for Evaluating Road Roughness using Low Cost Instrument) for calibration of Bump Integrator.

2. EQUIPMENT

MERLIN has a rigid frame 1.8 metre long with a wheel in front, a curved foot at the rear and a probe mid-way between the two which rests on the road surface. If the road surface was perfectly smooth, the probe would always lie on a straight line between the bottom of the wheel and the rear foot. On an uneven road surface the probe would usually be displaced above or below the line. A computer simulation shows that the spread of these displacements could be used to estimate on the standard roughness scale.

To measure the displacements, the probe is attached to a pivoted arm, at the other end of which a pointer moves over a chart. The arm has a mechanical amplification of 10 so that a movement of the probe of 1 mm will produce a pointer movement of 10 mm.

3. PROCEDURE

The roughness of a section of the road is measured by wheeling MERLIN along the road with the frame raised. Once every wheel revolution, the frame is lowered so that the probe and rear foot touch the ground and the resulting pointer position is recorded as a cross on the chart. Two hundred measurements are14

made to produce a histogram. The rougher the road surface, the greater is the variability of displacement. The speed of displacement has been found to correlate well with road roughness as measured on roughness scale. The width of the central 90 per cent of the histogram is measured from the chart and this can conveniently be converted directly into roughness from conversion equations that are available.

REFERENCES

  1. Road Research Laboratory - Report No 229, 1996
  2. World Bank Technical Paper No 45.15

Annexure-3

ROD AND LEVEL METHOD

1. INTRODUCTION

This specification covers the rod and level method for the calibration of bump integrator.

2. EQUIPMENT

The equipment required are as under:

3. PROCEDURE

3.1.

The procedure is as follows:

Since the vertical deviation in rod profile occur both in positive as well as negative directions they tend to average out over long distances. Two methods of profile analysis are used to avoid this cancellation and summarize meaningfully the deviations.

3.1.1. Root - mean - square deviation (RMSD) :

In this method, the amplitudes of the deviations are squared and averaged for the specific wavelength so that the values remain positive. The positive square root of the average is reported as RMSD for the specified wavelength.

3.1.2. Average rectified deviation (ARD) :

In this method, the absolute amplitude of the deviations are averaged for the specified wavelengths so that the value remains positive. The average is reported as the ARD for the specified wavelength.16